1. The _________ should be held before work on a project begins to ensure
agreement on the proposed schedule, methods to be used to complete the project
on schedule, change orders, and other critical project information.
A. Quality control meeting
B. Preconstruction conference
C. Safety briefing
D. Post-construction review
Answer: B
Rationale: The preconstruction conference should be held before work begins to align
all stakeholders on schedule, methods, change orders, and critical project information .
2. What is the correct hierarchy of construction documents from least to most
authoritative?
A. Plans, Standard specs, Supplemental specs, Special provisions
B. Standard drawings, Standard specs, Supplemental specs, Plans, Special provisions,
Special provisions copied notes
C. Special provisions, Plans, Standard specs, Standard drawings
D. Standard specs, Plans, Special provisions, Supplemental specs
Answer: B
Rationale: The hierarchy from least to most authoritative is: Standard drawings,
Standard specs, Supplemental specs, Plans, Special provisions, Special provisions copied
notes .
,3. Which construction documents detail approved additions and revisions to the
standard specifications?
A. Plans
B. Standard drawings
C. Supplemental specifications
D. Special provisions copied notes
Answer: C
Rationale: Supplemental specifications contain approved additions and revisions to the
standard specifications .
4. In terms of contracts, which of the following has the highest priority?
A. Standard specifications
B. Plans
C. Special Provision Copied Notes
D. Supplemental specifications
Answer: C
Rationale: Special Provision Copied Notes have the highest priority in the contract
documents hierarchy .
5. Daily meetings held at a project site or plant location that provide a forum for
the exchange of information are called:
A. Preconstruction conferences
B. Formal meetings
C. Informal meetings
D. Quality control meetings
Answer: C
Rationale: Daily informal meetings at project sites or plants provide a forum for
information exchange .
,6. If an unsafe work practice is noticed at the job site:
A. Report it at the end of the shift
B. Corrective action should be taken immediately, even if the paving operation must be
shut down
C. Document it and continue work
D. Notify the project manager only
Answer: B
Rationale: If an unsafe work practice is noticed, corrective action should be taken
immediately, even if the paving operation must be shut down until the unsafe practice is
changed .
7. _______ is the key to a safe work environment.
A. Safety equipment only
B. Proper training only
C. Communication only
D. Safety equipment, proper training, and communication
Answer: D
Rationale: Safety equipment, proper training, and communication are all essential
components of a safe work environment .
SECTION 2: TACK COAT & BONDING
(Questions 8-25)
8. This ensures an adequate bond between the existing pavement surface and the
new asphalt overlay so that slippage and delamination do not occur:
A. Prime coat
B. Tack coat
C. Seal coat
D. Fog seal
, Answer: B
Rationale: A tack coat ensures an adequate bond between the existing pavement
surface and the new asphalt overlay, preventing slippage and delamination .
9. Which tack coat can be used prior to May and after September?
A. Trackless
B. Conventional
C. Polymer-modified
D. Rapid-set
Answer: B
Rationale: Conventional tack coat can be used prior to May and after September .
10. Which tack coat can be used year round and must be used from May through
September?
A. Conventional
B. Trackless
C. Rapid-set
D. Slow-set
Answer: B
Rationale: Trackless tack coat can be used year round and must be used from May
through September .
11. What is the range of proper tack coat application in gallons per square yard?
A. 0.01 to 0.03
B. 0.05 to 0.10
C. 0.10 to 0.20
D. 0.20 to 0.30
Answer: B
Rationale: The proper tack coat application rate ranges from 0.05 to 0.10 gal/yd² .