CMT 210 Final Test with all Correct & 100% Verified
Answers |Guaranteed to Pass
What type of sequencing relationship is used when two activities should be completed at the
same time? ✔Correct Answer-Finish to finish
In most construction schedules, activity duration should be no shorter than ________?
✔Correct Answer-1 day
the three primary elements of a construction project are cost, ______, and quality. ✔Correct
Answer-time
the amount of the subcontractor agreement is normally based on a lump-sum bid by the
subcontractor to the contractor. (T/F) ✔Correct Answer-True
the cash flow curve is normally a(n) "_____" curve. ✔Correct Answer-S curve
If a firm employs ____ or more employees at any one time in the previous calendar year, it must
file OSHA Form 300 and Form 300A. ✔Correct Answer-11
AIA Document A201 requires that the claim be made within 21 days after recognizing the
charge. (T/F) ✔Correct Answer-T
the _______ is a plan for temporary facilities, material, material storage, and material handling
equipment on the jobsite. ✔Correct Answer-jobsite layout plan
a(n) _______ safety meeting is an on site meeting held with all workers and their supervisors
discussing hazards. ✔Correct Answer-Toolbox
The ______ is the principle manager of the work, oversees the subcontractor as the work is
being accomplished. ✔Correct Answer-superintendent
A _______ is a drawing or set of drawings produced by the contractor, supplier, manufacturer,
subcontractor, or fabricator. ✔Correct Answer-shop drawings
the term ______ is used for an unskilled person who has no training and is not enrolled in a
training program. ✔Correct Answer-helper
when a contractor employs union labor, a(n) ________ exists between the contractor and
union. ✔Correct Answer-Labor agreement or arrangement
Answers |Guaranteed to Pass
What type of sequencing relationship is used when two activities should be completed at the
same time? ✔Correct Answer-Finish to finish
In most construction schedules, activity duration should be no shorter than ________?
✔Correct Answer-1 day
the three primary elements of a construction project are cost, ______, and quality. ✔Correct
Answer-time
the amount of the subcontractor agreement is normally based on a lump-sum bid by the
subcontractor to the contractor. (T/F) ✔Correct Answer-True
the cash flow curve is normally a(n) "_____" curve. ✔Correct Answer-S curve
If a firm employs ____ or more employees at any one time in the previous calendar year, it must
file OSHA Form 300 and Form 300A. ✔Correct Answer-11
AIA Document A201 requires that the claim be made within 21 days after recognizing the
charge. (T/F) ✔Correct Answer-T
the _______ is a plan for temporary facilities, material, material storage, and material handling
equipment on the jobsite. ✔Correct Answer-jobsite layout plan
a(n) _______ safety meeting is an on site meeting held with all workers and their supervisors
discussing hazards. ✔Correct Answer-Toolbox
The ______ is the principle manager of the work, oversees the subcontractor as the work is
being accomplished. ✔Correct Answer-superintendent
A _______ is a drawing or set of drawings produced by the contractor, supplier, manufacturer,
subcontractor, or fabricator. ✔Correct Answer-shop drawings
the term ______ is used for an unskilled person who has no training and is not enrolled in a
training program. ✔Correct Answer-helper
when a contractor employs union labor, a(n) ________ exists between the contractor and
union. ✔Correct Answer-Labor agreement or arrangement