VERIFIED ANSWERS
False - CORRECT ANSWER (T/F) Fast tracking is when multiple specific scopes of
work on a project are being constructed at the same time
Design-Build - CORRECT ANSWER According to AGC, which delivery method can
use any of the procurement options?
True - CORRECT ANSWER (T/F) According to AGC, when someone labels a "typical"
characteristic as a "defining" characteristic, a hybrid is created
True - CORRECT ANSWER (T/F) According to AGC, several states prohibit any
element of price to be part of the selection process for contractors in public work
using CM at Risk
False - CORRECT ANSWER (T/F) The lump sum type of reimbursement is common
when projects are procured using Low Bid or Best Value: Fees
False - CORRECT ANSWER (T/F) A project manager's scope of responsibility is more
limited than a program manager's scope of responsibility
Fast-Track - CORRECT ANSWER According to AGC, the process of starting physical
construction while the design phase is still being completed is called
_________________.
, False - CORRECT ANSWER (T/F) According to a class handout, the goal of the
"Creative Phase" of the value engineering process is to narrow down the ideas
into the best few and work from there.
Code of Hammurabi - CORRECT ANSWER What are considered to be the first set of
recorded building codes?
False - CORRECT ANSWER (T/F) Qualification Based Selection is a procurement
process that is defined as a competition where price is only a small factor in the
final selection criterion
Partial documents that are used by the owner at the basis of pricing - CORRECT
ANSWER According to AGC, Bridging documents are defined as _____________.
Bronze - CORRECT ANSWER Which of the following is not certification level for
LEED
True - CORRECT ANSWER (T/F) The purpose of pre-qualification is to ensure that
those designers or constructors competing for and bidding on the work are
capable of performing the necessary services.
False - CORRECT ANSWER (T/F) According to AGC, a Project Manager typically
oversee the construction of multiple structures on the same site or handle
coordinated building efforts at multiple locations or under multiple contract