SECTION 1: Project Life Cycles (Definition, Predictive vs. Adaptive vs.
Hybrid) — 6 Questions
Q1: A project life cycle is best defined as which of the following?
A. The specific methodology used to develop project deliverables
B. The series of phases that a project passes through from start to completion
[CORRECT]
C. The organizational structure that governs resource allocation
D. The schedule baseline established during project initiation
Correct Answer: B
Rationale: Correct because the project life cycle is the series of phases that a project
passes through from start to completion, encompassing all the work of the project
regardless of the development approach selected.
Q2: Which of the following statements accurately describes the relationship between a
project life cycle and its development approach?
A. The development approach and project life cycle are identical and interchangeable
terms
, B. The project life cycle is influenced by the development approach but includes all the
work of the project [CORRECT]
C. The development approach determines the project life cycle exclusively, with no other
influencing factors
D. A project life cycle can only accommodate one development approach throughout its
duration
Correct Answer: B
Rationale: Correct because the project life cycle is influenced by the development
approach but includes all the work of the project, and a single life cycle can include
multiple development approaches and delivery cadences.
Q3: In a predictive life cycle, how is change typically managed?
A. Change is encouraged as a primary driver of innovation and value delivery
B. Change is not encouraged except as a way to prevent defects or correct
nonconforming project work [CORRECT]
C. Change is managed through constant feedback loops and iterative refinement
D. Change is prohibited entirely once the project baseline is established
Correct Answer: B
Rationale: Correct because predictive life cycles are plan-driven, and change is not
encouraged except as a way to prevent defects or correct nonconforming project work,
distinguishing them from adaptive approaches where change is expected.