2026 COMPLETE LECTURE NOTES KEY
CONCEPTS CASE ANALYSIS AND EXAM
REVIEW
the key benefit of the define activities process is:
rolling wave planning
an iterative planning technique in which the work to be accomplished in the
near term is planned in detail, while work further out in the future is
planned at a higher level
precedence diagramming method
PDM stands for...
PDM
a technique used for constructing a schedule model in which activities are
represented by nodes and are graphically linked by one or more logical
relationships to show the sequence in which the activities are to be
performed
sequence activities process
, the process of identifying and documenting relationships among the project
activities
it defines the logical sequence of work
the key benefit of the sequence activities process is:
dependency determination
a technique used to identify a type of dependency that is used to create the
logical relationships between predecessor or successor activities
project schedule network diagram
a graphical representation of the logical relationships among the project
schedule activities
project schedule network diagram
the ______ is the result of the precedence diagramming effort and is an
output of the sequence activities process
precedence relationship
the term used in the precedence diagramming method for a logical
relationship