When submitting an emergency notification how many days
does the state require for notice before commencing any mold
premeditation related activities?
- ANSWER-Next Business Day
What is the cost for filling a Mold State Notification? -
ANSWER-$25.00
What does MRC stand for? - ANSWER-Mold Remediation
Contractor
Not later than the _____th day after the date on which MRC
completes mold
remediation at the property the MRC shall provide a
certificate of Mold
remediation to the property owner. -
ANSWER-10
, True / False: A license holder may perform both mold
assessment and mold
remediation on the same project. -
ANSWER-False
How many years shall MRC maintain records for each
mold remediation
project? - ANSWER-3
Years
What are the 4 record requirements each mold remediation
project needs? - ANSWER-1. Before and after photographs of
the project.
2. Written Contract between all parties.
3. Invoices regarding mold remediation.
4. any other material required by the department.
Not later than the ____th day after the date of completion of the
mold remediation, the MRC shall provide the owner with copies
of all photographs. -
ANSWER-
10
When is the property owner not liable for damages related to
mold remediation
on property? - ANSWER-A certificate of mold remediation has
been issued for
the property and the damages accorded on or before the date
of the issued