C722- Project Management Exam UPDATED ACTUAL QUESTIONS AND CORRECT ANSWERS A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which aspect of project management applies to this firm's project? - CORRECT ANSWER Interdependent Tasks A firm begins its strategic business initiative of developing a new business model to enhance its competitiveness. What can be identified as a strategic business initiative for this firm? - CORRECT ANSWER Improvement in product design A firm begins a strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. - CORRECT ANSWER sponsor Which group is included in the five process groups? - CORRECT ANSWER group What does PRINCE2 stand for? - CORRECT ANSWER Environment PRojects IN a Controlled Project Closing process Which PMBOK process group is described as the delivery part of project management where the main activity happens? - CORRECT ANSWER Executing Which advantage does the functional (departmentalized) organizational structure provide for a firm with multiple projects? - CORRECT ANSWER Lines of authority are clear. Which two organizations are examples of organizations with the functional organizational structure? - CORRECT ANSWER (1) The U.S. Department of State and (2) The U.S Department of Energy

Voorbeeld van de inhoud

C722- Project Management Exam
UPDATED ACTUAL QUESTIONS AND
CORRECT ANSWERS
A firm begins its strategic business initiative of developing a new business model that will allow the
firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a
business management project. Which aspect of project management applies to this firm's project? -
CORRECT ANSWER Interdependent Tasks



A firm begins its strategic business initiative of developing a new business model to enhance its
competitiveness. What can be identified as a strategic business initiative for this firm? - CORRECT
ANSWER Improvement in product design



A firm begins a strategic business initiative of developing a new business model that will allow the
firm to deliver an efficient, tailored service to its customers. - CORRECT ANSWER Project
sponsor



Which group is included in the five process groups? - CORRECT ANSWER Closing process
group



What does PRINCE2 stand for? - CORRECT ANSWER PRojects IN a Controlled
Environment



Which PMBOK process group is described as the delivery part of project management where the
main activity happens? - CORRECT ANSWER Executing



Which advantage does the functional (departmentalized) organizational structure provide for a firm
with multiple projects? - CORRECT ANSWER Lines of authority are clear.



Which two organizations are examples of organizations with the functional organizational structure? -
CORRECT ANSWER (1) The U.S. Department of State and (2) The U.S Department of
Energy

, An organization expects to use a project management office (PMO) to support multiple projects that
will be implemented within a projectized organizational structure. Which implied effect is a benefit to
this organization? - CORRECT ANSWER Project team members gain access to historical data
from other projects.



Regardless of the organizational structure used to manage a project, an organization elects to use a
project management office (PMO). Which benefit will this organization gain? - CORRECT ANSWER
Projects will coordinate resource usage by monitoring the status of shared resources.



During a certain project phase, specific blueprints are drawn and approved, materials and labor costs
are estimated, prototypes are created, and work activities and tasks are identified. Also, quality
expectations, measurements, and costs are defined. During which project phase do these activities
occur? - CORRECT ANSWER Planning



Place the project activities in order of occurrence from first (1) to last (5). - CORRECT ANSWER
(1) Collecting customer requirements (2) Developing the work breakdown structure (3)
Working to produce project deliverables (4) Customers evaluating the project outcomes (5) Capturing
lessons learned



During which life cycle phase is the vast majority of the actual work to produce the project's
deliverables completed? - CORRECT ANSWER Executing



What is the correct term for an intermediate outcome of project work, such as a signed contract or
obtaining a construction permit? - CORRECT ANSWER Deliverable



Which deliverable from a work breakdown structure (WBS) is not specific enough to measure its
completion at project closure? - CORRECT ANSWER User training



The following table shows the Level 1 work breakdown structure (WBS) for Project A.



WBS ID Description

0.0 Project A

1.0 Project started

2.0 Feasiblity

3.0 Design

Documentinformatie

Geüpload op
21 juli 2026
Aantal pagina's
12
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$11.99

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Verkocht
69
Volgers
2
Items
10308
Laatst verkocht
1 week geleden



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen