WGU Project Management C722 Exam UPDATED ACTUAL QUESTIONS AND CORRECT ANSWERS Projects have a(n) ____________ start and end date. - CORRECT ANSWER Identify which of the following are business scenarios. - CORRECT ANSWER is at a five-year high and expected to continue to rise. AND Definite The price of oil New technology can provide smaller batteries that can be recharged by movement of the mobile device, extending battery life. Projects selected by an organization must be directly related to the organization's _____________. - CORRECT ANSWER Strategy What are the objectives of project management? - CORRECT ANSWER budget, and schedule True or False? Meeting scope, Project managers must not only manage people of all levels, but they must also manage costs, expectations, procurement, outside suppliers, and partners. - CORRECT ANSWER True It is important that project status meetings are: - CORRECT ANSWER regular and timely Which communication type is the best option when working in a widely dispersed virtual team? - CORRECT ANSWER Shared threaded discussion Which organization includes standards for Organizational Project Management Maturity (OPM3)? - CORRECT ANSWER Project Management Institute (PMI) Which organizational structure is used by government entities? - CORRECT ANSWER Functional

Content preview

WGU Project Management C722 Exam
UPDATED ACTUAL QUESTIONS AND
CORRECT ANSWERS
Projects have a(n) ____________ start and end date. - CORRECT ANSWER Definite



Identify which of the following are business scenarios. - CORRECT ANSWER The price of oil
is at a five-year high and expected to continue to rise.

AND

New technology can provide smaller batteries that can be recharged by movement of the mobile
device, extending battery life.



Projects selected by an organization must be directly related to the organization's _____________. -
CORRECT ANSWER Strategy



What are the objectives of project management? - CORRECT ANSWER Meeting scope,
budget, and schedule



True or False?

Project managers must not only manage people of all levels, but they must also manage costs,
expectations, procurement, outside suppliers, and partners. - CORRECT ANSWER True



It is important that project status meetings are: - CORRECT ANSWER regular and timely



Which communication type is the best option when working in a widely dispersed virtual team? -
CORRECT ANSWER Shared threaded discussion



Which organization includes standards for Organizational Project Management Maturity (OPM3)? -
CORRECT ANSWER Project Management Institute (PMI)



Which organizational structure is used by government entities? - CORRECT ANSWER
Functional

,Which applies to the Project Management Office (PMO)? - CORRECT ANSWER Tracks
"lessons learned" to be carried to new projects.

AND

Helps provide resources to projects as needed.

AND

Creates a repository for all project knowledge in the organization.



Project Management Offices (PMOs) can help align project investment to: - CORRECT ANSWER
Corporate strategy



In addition to the triple constraints, what other considerations may determine if the project is
successful? - CORRECT ANSWER The requirements in the scope adequately define the
project's objectives.



Which statement about projects, programs, and portfolios is correct? - CORRECT ANSWER A
group of programs or projects that support the same business goal makes up a portfolio.



You work at an automotive manufacturer. This company has the goal of being able to supply a full
family of passenger cars from small compact to large luxury.



There is a huge endeavor being undertaken to design and develop an entirely new small passenger car.
There are several groups of people working on different aspects of this endeavor: one group on the
engine, one on the transmission, one on navigation system, and so on. Each group has its scheduled
start and end dates and a definition of the unique product it will create.



Each of these groups is working on a _____________. - CORRECT ANSWER project



You are talking to a friend, Ted, who has renovation project management experience. You cannot
decide whether you want to take on the daunting task of being your own project manager. Ted tells
you that if you decide to manage the project, your first assignment will be to create the project
_____________. - CORRECT ANSWER Plan



You ask Ted what types of skills he thinks are critical in a project manager role. Ted thinks for a
minute, then responds, "I can think of three things right off the top of my head."

, What do you think are critical? - CORRECT ANSWER Conflict resolver, organization, and
ability to communicate verbally and in writing



What has the evolution of cloud computing done for project management? - CORRECT ANSWER
Provided a way to collaborate virtually



An organization's project management maturity level is determined by what? - CORRECT ANSWER
Adherence to standards and guidelines set by recognized professional organizations



In which type of organizational structure does the project manager and the functional manager "share"
authority? - CORRECT ANSWER Matrix



What are advantages of having a project management office? - CORRECT ANSWER Keeps a
central database of "lessons learned." AND Makes sure all projects implement best practices.



The base types of organizational structure are functional, projectized, and: - CORRECT ANSWER
Matrix



What is an example of information that might be found in a project proposal? - CORRECT ANSWER
Risks to the project



What concludes the project defining phase? - CORRECT ANSWER Creation and selection of
the project charter



Major project outcomes and deliverables, how the project will be completed, and a high-level estimate
of the cost and completion time are included in the: - CORRECT ANSWER project proposal



True or False?

During the executing phase, the project team may need to return to the planning phase in order to
make an adjustment to the budget, schedule, or scope. - CORRECT ANSWER True



The project deliverables and outcomes are created during the which phase of the project life cycle? -
CORRECT ANSWER Executing

Document information

Uploaded on
July 21, 2026
Number of pages
18
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Sold
69
Followers
2
Items
10308
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions