Ashworth College B06V Cost Estimating Assignment 4
Shannen Mansfield
Ashworth College
Cost Estimating
6/22/2026
1. Enlarge the footprint by five feet for accuracy and slope, then determine the volume
of topsoil to be removed and stockpiled if the thickness is 9
24 + 5 + 5 = 34ft
18 + 5 + 5 = 28ft
34 x 28 x 0.75 = 714cft
Topsoil to be removed
714cft/27cf per yd3 = 26yd3
Answer: 714cft or 26.44yd3
2. If no soil is to be stockpiled and the swell is 10 percent, how many truck loads will it
take to cart away from the site using 7 cy trucks?
Cubic yards of haul
26x 0.1 (10%) = 2.6 + 26 + 28.6
28.6/7cy = 4.085714286
Answer: 4 trucks
A cross section of the 24” wide continuous footing is shown. Assume this footing detail
applies to all footings throughout the building.
3. Determine the total linear feet of footing required. 24 + 18 + 18 + 24 + 10 = 94ft
Answer: 94FT