Purpose of Construction Quality Management Answer >>To assure that the
quality set by the plans and specifications is achieved
Reasoning behind the USACE/NAVFAC policy on CQM Answer >>The contractor
was either given great latitude in organizing the effort to get quality or given
specific expectations and processes. Now a structured methodology has been
chosen to standardize the process
Characteristics that are specific to the construction industry. Answer >>The
construction industry has become highly specialized because of the changing
market. Increased technology and regulation have resulted in increasing numbers
of specialty contractors
Define Contractor Quality Control (CQC) Answer >>primary responsibility for
producing construction through compliance with plans, specifications, and
accepted standards of the industry.
Define Government Quality Assurance (QA) Answer >>assure that the quality set
by the plans and specifications is achieved.
What establishes the Construction quality requirements? Answer >>
, USACE
Define CQM Answer >>performance of tasks, which ensure that construction is
performed according to plans and specifications, on time, within a defined
budget, and a safe work environment.
What are the two principal areas of CQM activity? Answer >>
Define first principal Answer >>
Define second principal Answer >>
What are the benefits of CQM to the contractor? To the Government? Answer
>>
What two factors have caused the construction industry to become highly
specialized Answer >>
Why are construction projects difficult to manage? Answer >>
What factors will influence both the Government and the construction industry in
the future Answer >>
Differentiate between "inspection" and "control." Answer >>
Describe, in general, the contractor's and the Government's responsibilities in
CQM. Answer >>