CEM 100 Ch.11 Questions with Correct
Answers
critical path method (CPM)

project management system that is widely used for construction time control.

the earliest time an activity can begin based on network calculations made by a

computer (and translated into calendar dates)

early start

On an _______ schedule, the ________ date occurs the day after the number of working

days listed on the chart.

early start

the earliest time an activity can finish based on network calculations made by a

computer (and translated into calendar dates)

early finish

the latest time an activity can start without delaying project completion. Total floats on

a project allow a degree of flexibility in the start date on an activity.

late start

the latest time an activity can finish without delaying project completion. Total floats on

a project allow a degree of flexibility in the end date on an activity.

late finish

the chain of activities that control the overall project completion.

critical path

,Reduction of the overall project duration can only be accomplished by reducing the

___________

critical path

occur when contractors make financial claims for delay damages and time extensions

when it causes a delay on contract performance.

Delay claims

What can demonstrate the true effect of a delay?

CPM Schedules

gives the amount of time an activity can be delayed without delaying the completion of

the whole project. This gives a certain amount of leeway for scheduling.

Float

________ gives the greatest amount of time allowable to finish the activity without

delaying the project completion date.

total float (TF)

What is Total Float also known as?

total slack time or total slack

Since this affects other work scheduled before and after the activity with the float, a new

_____________ would be developed.

critical path

_________ is the latest an activity can be completed without affecting other work or the

completion dates of the project.

, Free float (FF)

What is Free float also known as?

free slack or free slack time

is a scheduling method that was developed by the US Navy with Booz Allen Hamilton &

Lockheed on the Polaris Missile/Submarine Program in late 1950s. This method was

first used in building the Polaris nuclear-powered submarine and its strategic ballistic

missile system.

Program Evaluation and Review Technique (PERT)

With the ____ method, the accurate time table for completion and the available

resources are unknown.

PERT

method illustrates where a project has repetitive work blocks. This is represented as a

single line on a graph and represents linear projects such as pipelines, electrical

transmission lines, and highways. On this chart, the activities are represented as lines

that run vertically, and these represent the work rate (includes all of the activities)

needed to complete the project on time.

line-of-balance (LOB)

is a track trending curve that is a graphical representation of progress over a period of

time. The curve is created by vertical bars. These may also be used for historical data to

visualize project trends and variations.

'S' Curve

Document information

Uploaded on
July 18, 2026
Number of pages
18
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
KenAli
2.6
(18)
Sold
111
Followers
5
Items
23367
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions