Examination: S-Tier Universal
Mastery Test Bank
PART 0: THE (Table of Contents)
Section Designation Cognitive Progression Focus Area
PART I: The Preview Baseline Initialization Core Axioms, Statutory
Overrides, Testing Parameters
PART II: Tier 1 Foundational Syntax (Q1–Q10) "Hard Deck" Definitions, DCA
Amendments, Base Formulas
PART II: Tier 2 Complex Application Variable Shifting, Hardware
(Q11–Q20) Substitution, System Upgrades
PART II: Tier 3 Grandmaster Synthesis High-Stakes Troubleshooting,
(Q21–30) Cross-Disciplinary Integration
PART I: THE Preview
Mastery of the Georgia Electrical Contractor Examination requires more than rote memorization;
it demands the fluid application of the National Electrical Code (NEC) integrated seamlessly with
state-specific Department of Community Affairs (DCA) statutory overrides. The ensuing
assessment forges elite theoretical and practical competence, ensuring the candidate's
academic rigor translates directly into flawless commercial, industrial, and residential execution.
The "Critical Axioms" Cheat Sheet
● The DCA GFCI/AFCI Decimation: While the national NFPA 70 text expanded GFCI and
AFCI mandates aggressively, Georgia's State Codes Advisory Committee (SCAC)
actively stripped them back. AFCI protection is no longer required for kitchens and
laundry areas. Furthermore, GFCI is eliminated for refrigerators (unless serving
countertop surfaces), electric ranges, wall-mounted ovens, and clothes dryers.
● The SPD Dwelling Exemption: The 2026 NEC mandates Surge-Protective Devices
(SPDs) globally for dwellings under Articles 215.18(A), 225.42(A), and 230.67(A). Georgia
state amendments explicitly and permanently exempt one- and two-family dwellings from
this requirement.
● The Article 120 Migration: In the 2026 NEC cycle, foundational load calculations
previously housed in Article 220 have been relocated to Article 120, fundamentally
, altering open-book navigation strategy during the PSI exam.
● The Class Scope Boundary: A Georgia Class I Restricted license legally caps at
single-phase installations not exceeding 200 amperes at the service drop; any parameter
exceeding this absolute limit—including any three-phase power—requires a Class II
Unrestricted license.
● The PSI Blueprint Reality: The Georgia Class II exam is a gruelling 8-hour, two-part
gauntlet presenting 162 total questions. However, exactly 140 questions are scored,
testing both Technical Functions and Administrative/Law regulations.
PART II: THE ELITE TEST BANK
Tier 1: Foundational Syntax & Application
Q1: A Class I electrical contractor is roughing in a new 200-ampere service for a single-family
dwelling in Savannah, Georgia. Based on the 2026 National Electrical Code integrated with the
current Georgia DCA Amendments, what is the required protocol for Surge-Protective Devices
(SPDs) at the main service disconnect? A) A Type 1 or Type 2 SPD must be installed to comply
with NEC 230.67(A). B) An SPD is strictly prohibited on single-phase 200-ampere residential
services. C) The contractor is entirely exempt from installing an SPD for this specific occupancy.
D) The contractor must install a Type 3 point-of-use SPD at the kitchen receptacles to satisfy the
service requirement.
● The Answer: C (The contractor is entirely exempt from installing an SPD for this specific
occupancy.)
● Distractor Analysis:
○ A is incorrect: While the unamended 2026 NEC 230.67(A) mandates SPDs for all
dwelling units, this ignores the superseding state-level amendment.
○ B is incorrect: SPDs are not prohibited; they are highly recommended as an
engineering best practice, but they are not legally mandated.
○ D is incorrect: Type 3 SPDs are localized utilization devices and do not satisfy
service-level overvoltage protection requirements.
The Mentor's Analysis: Statutory amendments legally overwrite the base model code. The
Georgia DCA specifically amended Articles 215.18(A), 225.42(A), and 230.67(A) to add a
universal exception: one- and two-family dwellings are completely exempt from the SPD
mandate. By utilizing the Georgia DCA Amendments, you bypass the common trap of
answering based purely on the national NFPA 70 text. Professional/Academic Intuition:
Never apply a national safety mandate without first verifying the existence of a state-level
statutory exemption.
Q2: A Journeyman is wiring a new residential kitchen featuring an open-concept island
countertop. The homeowner specifically requests that the countertop remain flat and
uninterrupted by pop-up electrical assemblies. Under the Georgia amendments to the 2026
NEC (Section 210.52(C)(3)), which installation method is MOST APPROPRIATE? A) The
contractor must refuse the request, as pop-up assemblies are the only legal method for island
receptacles. B) The contractor may install the receptacle on the side of the island, provided it is
mounted not more than 12 inches below the countertop and the overhang does not exceed 6
inches. C) The contractor may omit the receptacle entirely, as islands in open-concept kitchens
no longer require power. D) The contractor may install a standard wall receptacle 36 inches
away from the island to satisfy the requirement.
, ● The Answer: B (The contractor may install the receptacle on the side of the island,
provided it is mounted not more than 12 inches below the countertop and the overhang
does not exceed 6 inches.)
● Distractor Analysis:
○ A is incorrect: The 2020 NEC pushed heavily toward pop-up assemblies, but
Georgia's SCAC explicitly reverted this code to allow below-countertop mounting.
○ C is incorrect: Receptacles are strictly required for island and peninsular
countertops with a long dimension of 24 inches or greater.
○ D is incorrect: Receptacles satisfying the island requirement must be physically
located on or immediately adjacent to the island surface itself.
The Mentor's Analysis: Code cycles frequently oscillate between strict safety mandates and
practical field realities. Georgia's amendment to 210.52(C)(3) restores the installer's ability to
mount receptacles up to 12 inches below the surface of an island, deliberately reversing the
national push for mandatory pop-up devices. By utilizing local installation allowances, you
preserve the architectural intent without violating the law. Professional/Academic Intuition:
State boards frequently amend the NEC to preserve aesthetic and practical flexibility;
memorize the specific allowances that deviate from the national text.
Q3: During the PSI-administered Georgia Electrical Contractor Class II examination, a
candidate is instructed to calculate the total feeder load for a 12-unit apartment complex. Under
the updated structure of the 2026 NEC, to which primary Article must the candidate immediately
navigate? A) Article 220 B) Article 210 C) Article 120 D) Article 310
● The Answer: C (Article 120)
● Distractor Analysis:
○ A is incorrect: Article 220 housed load calculations for decades up through the 2023
NEC, making this a highly lethal trap for candidates relying on legacy muscle
memory.
○ B is incorrect: Article 210 governs the ratings and requirements of branch circuits,
not the macro-level calculation of feeder loads.
○ D is incorrect: Article 310 governs the physical properties and ampacities of
conductors, which are selected after the load is calculated.
The Mentor's Analysis: Open-book exam success is dictated entirely by spatial awareness
and indexing speed. The 2026 NEC fundamentally reorganized its architecture, tearing load
calculations out of Article 220 and relocating them to Article 120 to serve as a foundational
Chapter 1 baseline. By utilizing updated code architecture, you bypass the fatal error of
searching outdated tabs while the clock is running. Professional/Academic Intuition: When
testing under the 2026 NEC, overwrite your legacy memory: load calculations live in
Chapter 1.
Q4: A contractor is preparing to wire a residential laundry room in Atlanta. The design includes
a 120-volt receptacle for the washing machine and a 240-volt receptacle for the clothes dryer.
Based strictly on the Georgia SCAC amendments to the NEC, which specific protection scheme
is REQUIRED for these circuits? A) Both circuits must feature dual-function AFCI/GFCI
protection. B) The 120-volt washing machine requires GFCI, but the 240-volt clothes dryer is
explicitly exempt from GFCI, and both are exempt from AFCI. C) Both circuits are fully exempt
from GFCI protection, but require AFCI protection. D) The 240-volt dryer requires GFCI under
210.8(D), but the washing machine is exempt.
● The Answer: B (The 120-volt washing machine requires GFCI, but the 240-volt clothes
dryer is explicitly exempt from GFCI, and both are exempt from AFCI.)
● Distractor Analysis: