Question.
1. Before performing plumbing work requiring a state license
in Louisiana, a contractor should first:
A. Obtain only a local business license
B. Begin work and apply later
C. Hold the appropriate Louisiana plumbing license before
contracting for regulated work
D. Only register with the IRS
Answer: C
Rationale: Louisiana requires individuals and businesses
performing regulated plumbing work to hold the proper state
,licensing credentials before engaging in covered contracting
activities.
2. The primary purpose of a plumbing trap is to:
A. Increase water pressure
B. Filter sediment
C. Prevent sewer gases from entering occupied spaces
D. Improve drainage speed
Answer: C
Rationale: A properly installed trap maintains a water seal that
blocks sewer gases while allowing wastewater to flow through
the drainage system.
3. A vent system primarily functions to:
A. Carry wastewater
B. Remove solids
C. Protect trap seals and maintain proper air pressure within
the drainage system
D. Heat water lines
Answer: C
, Rationale: Venting equalizes pressure in the drainage system,
preventing trap siphonage and ensuring efficient fixture
drainage.
4. Which pipe material is commonly approved for residential
potable water distribution?
A. ABS DWV only
B. Clay tile
C. PEX
D. Corrugated drain pipe
Answer: C
Rationale: PEX is widely approved for potable water systems
where permitted by applicable plumbing codes and
manufacturer installation requirements.
5. Water hammer is caused by:
A. Excessive pipe insulation
B. Low water temperature
C. A sudden stoppage of flowing water
D. Excessive venting
Answer: C