An architect hires a structural engineer consultant for a new condominium project.
Five days before the design document drawings are due, the owner requests that a
rooftop garden and patio be included in the project. The structural engineer sends an
e-mail to the architect, requesting additional time and compensation for the
incorporation of the new roof modifications.


If an e-mail is an approved form of documentation according to the consultant
contract, what action should the architect take?
Forward the e-mail request with a description to the owner for review and approval.
Attach the e-mail to the owner's design document deliverables and invoice for
payment.
Reply to the e-mail asking the engineer to send their request to the architect in the
form of a letter.


Give this one a try later!

, CORRECT RESPONSE
Forward the e-mail request with a description to the owner for review and
approval.
Per the AIA B101 agreement, any adjustments to the schedule and estimate
must be submitted to the owner for approval. As e-mail has been deemed
an approved form of documentation in the architect-consultant agreement,
so the architect should not request correspondence in the form of a letter.
The architect should incorporate the engineer's communication into their
correspondence with the owner.
Topic: Contracts




Early in the construction documents phase of a project, a fire protection engineer
alerts the architect that the architect improperly classified the materials planned to be
stored in a warehouse space. The architect will need to revise the analysis of the
materials so that the fire protection engineer can correctly plan sprinkler coverage
and fire pump sizing.


What should the architect do first to respond to the lack of coordination?
Develop and submit a request for additional services.
Identify and take corrective actions to modify the project work plan.
Advise the owner of the design conditions and any impact on the schedule.


Give this one a try later!


CORRECT RESPONSE
Identify and take corrective actions to modify the project work plan.
Identifying and taking corrective action if a project is not performing
according to the project work plan is the first step the architect should take.
The architect must alert the owner of the situation but should first identify
the root cause of the error and define a path forward to resolve it prior to
the discussion with the owner.
Topic: Project Work Planning

, A university hires an architect to design a renovation and addition to a performing arts
center. The university wants to use an integrated project delivery method and contract
with a series of consultants who will each coordinate their scope of work with the
architect. The work is to be executed in multiple phases and includes the following:
Restore the original facade of the existing facility built in 1905.
Convert the existing sloped concrete floor performance hall into a new flat floor
performance space.
Renovate existing classrooms to provide new advanced audio and video laboratories.
Design a performance hall addition connected to the existing facility by an elevated
walkway.
Identify and address any AHJ or accessibility issues in the existing facility.
Who should the architect recommend the university hire before the schematic design
phase? Check the four that apply.
General contractor
Lighting designer
Geotechnical engineer
Commissioning agent
Historical preservationist
Construction manager


Give this one a try later!

Document information

Uploaded on
July 17, 2026
Number of pages
17
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$10.50

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
CLASSROOMTEST
3.4
(10)
Sold
47
Followers
2
Items
7464
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions