NCARB Exam | Verified Exam Questions and Answers | Latest Updated Study Material 2026

Document preview thumbnail
Preview 2 out of 8 pages

NCARB Exam | Verified Exam Questions and Answers | Latest Updated Study Material 2026

Content preview

NCARB Exam | Verified Exam Questions and Answers | Latest Updated
Study Material 2026

Question:

1. Black mold is discovered nine
months after building occupancy
and owner informs architect it was
due to improper installation. What 2. Meet with the owner and facilities manager to review
are two actions the architect should operations at no additional cost (Owner can request a
take?
Answer:

1. Instruct the owner to notify the original contractor
about the concern
meeting with the architect to review facility operations
and performance at no additional cost for up to one
year from date of substantial completion per B101)

Question:

2. Underpinning
Answer:

process of rebuilding or strengthening the foundation
of an existing building

Question:

3. The contractor and owner are in a Amend the contract to include a bonus provision to meet
dispute of reasoning behind pro-
ject delays. The owner's primary
concerns are holding to substantial on time. It bypasses the disputed issue of responsibility
completion date in the contract and for delays and focuses efforts on the owner's goal of
avoiding legal proceedings. What
should the architect recommend to
the owner?
Answer:

the stipulated substantial completion date. A bonus is a
viable way of incentivizing a contractor to complete work
meeting the substantial completion date.

, Question:

4. Hard costs of construction, defined concrete repairs, masonry repairs, landscape restora-
Answer:

as cost of materials, labor, and nec- tion
essary equipment

Question:

5. Overhead and Soft costs of con-
struction
Answer:

general conditions, overhead, profit, performance
bond, engineering

Question:

6. Owner visits the site during con-
struction and requests a redesign
of the restrooms without consult-
ing the architect. The contractor be- changes
gins the owner's requested alter-
Answer:

1. Reject change order #1 from contractor
2. Request additional design services from owner
3. Issue revised drawings that include necessary code
ations and submits change order
#1 to the architect. The architect
reviews the modifications at the job
site and identifies code violations
that will require a major redesign.
How should architect proceed?

Question:

7. An architect finds items of noncon- 1. Issue a field observation report listing all rejected
forming work during a construc-
tion site punch walk. Damaged ceil- 2. Determine the source of the nonconforming work in
ing tiles, malfunctioning light fix-
tures, and portions of the rubber
wall base that have not adhered will
all need to be corrected before sub-
stantial completion.

Document information

Uploaded on
July 16, 2026
Number of pages
8
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
5
Followers
0
Items
4027
Last sold
1 week ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions