Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 3 out of 23 pages
Exam (elaborations)

Project Management -UNIT SEVEN Latest Premium Exam Questions and Answers with Verified Solutions | Latest Updated 2026

Document preview thumbnail
Preview 3 out of 23 pages

Project Management -UNIT SEVEN Latest Premium Exam Questions and Answers with Verified Solutions | Latest Updated 2026

Content preview

Project Management -UNIT SEVEN Latest
Premium Exam Questions and Answers with
Verified Solutions | Latest Updated 2026



A major component of the time Time for the delivery of products
estimates will be labor hours, (ordering/vendor
which lead time)
will feed back to the budgeting Time for products to cure (drying time for
process to ensure that appropriate paint and
labor dollars have been allocated. concrete)
Other time considerations include: Time to get necessary equipment put in
place


Duration estimation techniques fall deterministic and probabilistic.
into two general categories:

,Deterministic duration estimation techniques are
appropriate
when the activity durations are very
predictable.
requires that the team expert provide a
reliable
estimate of the time necessary to complete
the
activity.This method is also called the
one-point
estimate method because the expert
provides a
single estimate for an activity based on
either his or
her own knowledge or historical
information


Probabilistic duration estimation techniques are used
when
there is uncertainty in how long an activity
will take.

, The second probabilistic method is the beta distribution or weighted
average. The
beta distribution still uses the three
estimates
(optimistic, most likely, and pessimistic)
but places
emphasis on the most likely estimate.The
formula
for the beta distribution places emphasis
on the
most likely estimate. This is accomplished
by
multiplying the most likely estimate (M) by
a factor
of four.


The first probabilistic approach is the triangular distribution or simple
average. The
three estimates are averaged together.The
experts
are asked to provide an optimistic estimate
(O), a
pessimistic estimate (P), and a most likely
estimate
(M).


Project management often uses duration
the Correct! Duration is used to describe the
term________to describe the number
number of of time periods required to complete a
time periods required to complete portion of
some portion of the work. the work.

Document information

Uploaded on
July 14, 2026
Number of pages
23
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$14.98

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
5
Followers
0
Items
9781
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions