Process of moving soil or rock from one location to another – Correct Answer earthmoving
Examples of earthmoving: - Correct Answer excavating
Loading
Hauling
Spreading
Compacting
Grading
Three-link earthwork system: - Correct Answer excavate and load
Haul/dump/return
Spread and compact
Every construction project is a _________ undertaking. Therefore, __________ is undertaken
to understand the problems and to develop courses of action. – Correct Answer unique
Planning
Planning steps for earthwork construction: - Correct Answer review the contract
documents
Study the plans
Plan the work
Perform quantity take-off
Determine costs
, A site visit is strongly recommended to relate the __________________ to the ______________.
– Correct Answer physical site characteristics
Work details
What steps do you take when you visit the site? – Correct Answer examine the materials
and make sure it matches what the lab reports say
What are the steps after the site visit? – Correct Answer the planner determines the
quantity of materials that will have to be furnished or moved
Must be as accurate as possible and should be based on all available engineering and
design data – Correct Answer quantity take-off
What must the planner do during the take-off? – Correct Answer make decisions
concerning equipment needs, sequence of operations, and crew size
What is the constructor looking for in the material? – Correct Answer how the material will
handle during the construction process
The most commonly used parameter for specifying construction operations because there
is a correlation between a soil’s physical properties and its density – Correct Answer
density
3 basic components of soil: - Correct Answer solids, water, air
Unit of soil: - Correct Answer pounds per cubic yard
Pounds per cubic foot
Kilograms per cubic meters
Latest Update
Process of moving soil or rock from one location to another – Correct Answer earthmoving
Examples of earthmoving: - Correct Answer excavating
Loading
Hauling
Spreading
Compacting
Grading
Three-link earthwork system: - Correct Answer excavate and load
Haul/dump/return
Spread and compact
Every construction project is a _________ undertaking. Therefore, __________ is undertaken
to understand the problems and to develop courses of action. – Correct Answer unique
Planning
Planning steps for earthwork construction: - Correct Answer review the contract
documents
Study the plans
Plan the work
Perform quantity take-off
Determine costs
, A site visit is strongly recommended to relate the __________________ to the ______________.
– Correct Answer physical site characteristics
Work details
What steps do you take when you visit the site? – Correct Answer examine the materials
and make sure it matches what the lab reports say
What are the steps after the site visit? – Correct Answer the planner determines the
quantity of materials that will have to be furnished or moved
Must be as accurate as possible and should be based on all available engineering and
design data – Correct Answer quantity take-off
What must the planner do during the take-off? – Correct Answer make decisions
concerning equipment needs, sequence of operations, and crew size
What is the constructor looking for in the material? – Correct Answer how the material will
handle during the construction process
The most commonly used parameter for specifying construction operations because there
is a correlation between a soil’s physical properties and its density – Correct Answer
density
3 basic components of soil: - Correct Answer solids, water, air
Unit of soil: - Correct Answer pounds per cubic yard
Pounds per cubic foot
Kilograms per cubic meters