⩥60 days. Answer: Deadline to file a lien after a "notice of completion"
is filed. A.R.S. § 33-993(A)
⩥120 days. Answer: Deadline to file a lien after "completion," if a notice
of completion is not filed. A.R.S. § 33-993(A
⩥6 months. Answer: Deadline for enforcing a lien (by filing a lawsuit).
⩥10 days. Answer: Deadline to dispute a lien after notice of owner's
intent to retain payment for the lien from payment to the contractor.
A.R.S. § 33-994
⩥20 days. Answer: Deadline for releasing a lien that has been paid in
full or following written request, to avoid owing penalties and damages.
A.R.S. § 33-1006
⩥a contractor license is required when the total cost, including materials
is more than. Answer: $1000
, ⩥which state agency has the authority to issue a contractor license.
Answer: ROC
⩥what is the role of the ROC. Answer: ALL OF THE ABOVE
⩥if you have a B- general license which of the items below must be
subcontracted ?. Answer: all of the above
-repairing an hvac
-installing a pool
-wiring a homes electrical circuit
⩥which of the following commercial license classifications is permitted
to subcontract electical work. Answer: B-1 General Commercial
Contractor
⩥A B- general residential contractor must subcontract what type of
work. Answer: electrical, boilers, and water wells
⩥what business type is eligible for a contractor license. Answer: llc, sole
prop, and partnership
EXAMINATION SCRIPT 2026 QUESTIONS
WITH ANSWERS GRADED A+
⩥60 days. Answer: Deadline to file a lien after a "notice of completion"
is filed. A.R.S. § 33-993(A)
⩥120 days. Answer: Deadline to file a lien after "completion," if a notice
of completion is not filed. A.R.S. § 33-993(A
⩥6 months. Answer: Deadline for enforcing a lien (by filing a lawsuit).
⩥10 days. Answer: Deadline to dispute a lien after notice of owner's
intent to retain payment for the lien from payment to the contractor.
A.R.S. § 33-994
⩥20 days. Answer: Deadline for releasing a lien that has been paid in
full or following written request, to avoid owing penalties and damages.
A.R.S. § 33-1006
⩥a contractor license is required when the total cost, including materials
is more than. Answer: $1000
, ⩥which state agency has the authority to issue a contractor license.
Answer: ROC
⩥what is the role of the ROC. Answer: ALL OF THE ABOVE
⩥if you have a B- general license which of the items below must be
subcontracted ?. Answer: all of the above
-repairing an hvac
-installing a pool
-wiring a homes electrical circuit
⩥which of the following commercial license classifications is permitted
to subcontract electical work. Answer: B-1 General Commercial
Contractor
⩥A B- general residential contractor must subcontract what type of
work. Answer: electrical, boilers, and water wells
⩥what business type is eligible for a contractor license. Answer: llc, sole
prop, and partnership