Q: Most emergency work orders should be written by production/operations. (T/F)
Answer:
True
Q: It should be common practice for operators to perform PMs. (T/F)
Answer:
True
Q: The P-F interval can be applied to visual inspections. (T/F)
Answer:
True
Q: The best method of measuring the reliability of an asset is by counting downtime
events. (T/F)
Answer:
True
,CMRP Practice Questions and Answers with Verified Solutions | Latest
2026 Update
Q: The primary purpose of scheduling is to coordinate maintenance jobs for
greatest utilization of
Answer:
maintenance resources. (T/F) True
Q: What percentage of your assets should be ranked critical based on the risk to
business?
Answer:
Less than 20%
Q: Vibration monitoring can detect uniform impeller wear. (T/F)
Answer:
False
,CMRP Practice Questions and Answers with Verified Solutions | Latest
2026 Update
Q: Understanding the known and likely causes of failures can help design a
maintenance strategy
Answer:
for an asset to prevent or predict failure. (T/F) True
Q: Reliability can be improved easily after a maintenance plan has been put into
operation. (T/F)
Answer:
False
Q: What percentage of maintenance work should be proactive?
Answer:
85% or more
, CMRP Practice Questions and Answers with Verified Solutions | Latest
2026 Update
Q: MTBF is measured by operating time divided by the number of failures of an
asset. (T/F)
Answer:
True
Q: Maintenance cost will decrease as reliability increases. (T/F)
Answer:
True
Q: The "F" on the P-F interval indicates that equipment is still functioning. (T/F)
Answer:
False
Q: A rule of thumb is that, on average, an experienced planner can plan work for
how many craft people?
Answer:
15