1. What is the primary purpose of Construction Quality
Management (CQM)?
A. To reduce construction costs only
B. To ensure compliance with contract requirements
C. To speed up project completion regardless of quality
D. To eliminate all inspections
Rationale: CQM focuses on ensuring that construction meets all
specified contract standards and requirements.
Correct Answer: B
2. Who is ultimately responsible for quality control on a
construction project?
A. Project owner
B. Quality assurance inspector
C. Contractor
D. Local government
,Rationale: The contractor is responsible for producing work
that meets contract requirements.
Correct Answer: C
3. What is Quality Assurance (QA)?
A. Contractor’s internal inspection system
B. Government or owner verification of quality processes
C. Worker training program
D. Material procurement process
Rationale: QA is performed by the owner or their
representatives to verify compliance.
Correct Answer: B
4. What is Quality Control (QC)?
A. Independent audit by third party
B. Contractor’s system to ensure quality work
C. Final project inspection
D. Government approval process
Rationale: QC is the contractor’s responsibility to ensure
standards are met.
Correct Answer: B
5. What document defines project quality requirements?
,A. Payroll records
B. Construction schedule
C. Contract specifications
D. Safety manual
Rationale: Specifications detail material, methods, and
performance requirements.
Correct Answer: C
6. What is the first step in a Quality Control program?
A. Final inspection
B. Deficiency correction
C. Preparatory phase
D. Payment approval
Rationale: QC begins before work starts with preparatory
planning.
Correct Answer: C
7. What is a three-phase inspection system?
A. Design, build, inspect
B. Planning, budgeting, execution
C. Preparatory, initial, follow-up
D. QA, QC, audit
, Rationale: The system includes preparatory, initial, and follow-
up phases.
Correct Answer: C
8. During which phase is the first installed work segment
inspected?
A. Final phase
B. Initial phase
C. Preparatory phase
D. Closeout phase
Rationale: Initial phase involves checking first work installation.
Correct Answer: B
9. What is a deficiency in construction terms?
A. Completed work ahead of schedule
B. Work that does not meet specifications
C. Approved design change
D. Completed inspection report
Rationale: Deficiency means non-conforming or defective work.
Correct Answer: B