A confidence vote is taken at the end of a PI planning event after
dependencies are resolved and risks are addressed. What best
describes the process of the confidence vote? - ANSWER-??? The
Teams and the ARTs vote???
Building a problem-solving culture is an example of which Safe core
value? - ANSWER-Relentless improvement
During the final plan review ART PI risks are Roamed. What do the
letters in ROAM represent? - ANSWER-Resolved, owned, accepted,
mitigated
During the PI Planning event, when are planning adjustments agreed
upon? - ANSWER-During the management review and problem-
solving
, How does Safe describe Customer Centricity? - ANSWER-As a mindset
focused on Customer behaviors that produce the best innovations
How does Safe provide a second operating system that enables
Business Agility? - ANSWER-By focusing on customers, products,
innovation, and growth
How does Safe recommend using a second operating system to deliver
value? - ANSWER-Organize development around the flow of value
while maintaining the hierarchies
How is the flow of portfolio Epics managed? - ANSWER-In the Portfolio
Kanban
In the ART Kanban some steps have work in process (WIIP) limits. Why
is this necessary? - ANSWER-To ensure large queues are not forming
On day two of PI Planning, management presents adjustments based
on the previous day's management review and problem-solving
meeting. What is one possible type of adjustment they could make -
ANSWER-Adjust business priorities
Restoring the speed and innovation of the entrepreneurial network
while leveraging the stability of the hierarchical system is a benefit of
what? - ANSWER-Dual operating system
Reviewing the organization's architecture vision during the first day of
PI P{landing is an example of what Safe core value? - ANSWER-
Alignment
The analyzing step of the portfolio Kanban system has a new Epic with
a completed Lean business case. What best describes the next step for