Advanced WGU C954 Information
Technology Management OA Practice Exam
Multiple Choice Questions (MCQs) with
Answers and Explanations
Questions 1–30
1. An organization's executive leadership wants every IT investment to directly
support corporate strategic objectives. Which governance principle best
addresses this requirement?
A. Minimizing capital expenditures
B. Delegating all technology decisions to system administrators
C. Aligning IT strategy with business strategy
D. Outsourcing all non-core IT services
Explanation: Strategic alignment ensures that technology initiatives support organizational
goals, maximizing business value and improving resource allocation.
2. A CIO proposes replacing several departmental databases with a centralized
enterprise platform. Which primary benefit is most likely to result?
A. Increased data redundancy
B. Reduced data consistency
C. Improved enterprise-wide data integration
D. Elimination of cybersecurity risks
Explanation: Centralized enterprise databases improve data consistency, reduce duplication,
and facilitate organization-wide reporting.
3. During a software implementation, users continually request new features
after development has begun, delaying project completion. This situation is best
described as:
A. Risk transference
, B. Business continuity
C. Scope creep
D. Benchmarking
Explanation: Scope creep occurs when project requirements expand without corresponding
adjustments to schedule, budget, or resources.
4. Which project management constraint is most directly affected when
additional features are added without increasing the budget?
A. Organizational culture
B. Vendor selection
C. Project schedule
D. Regulatory compliance
Explanation: Additional work generally requires more time when financial resources remain
unchanged.
5. A project manager identifies a potential cybersecurity threat that has a low
probability but extremely high business impact. What is the most appropriate
first step?
A. Ignore the threat
B. Accept the risk automatically
C. Assess and document the risk before determining a response strategy
D. Purchase additional hardware immediately
Explanation: Risk management begins with identification and assessment before mitigation,
transfer, avoidance, or acceptance decisions.
6. Which document formally authorizes a project and grants authority to the
project manager?
A. Risk register
B. Work breakdown structure
Technology Management OA Practice Exam
Multiple Choice Questions (MCQs) with
Answers and Explanations
Questions 1–30
1. An organization's executive leadership wants every IT investment to directly
support corporate strategic objectives. Which governance principle best
addresses this requirement?
A. Minimizing capital expenditures
B. Delegating all technology decisions to system administrators
C. Aligning IT strategy with business strategy
D. Outsourcing all non-core IT services
Explanation: Strategic alignment ensures that technology initiatives support organizational
goals, maximizing business value and improving resource allocation.
2. A CIO proposes replacing several departmental databases with a centralized
enterprise platform. Which primary benefit is most likely to result?
A. Increased data redundancy
B. Reduced data consistency
C. Improved enterprise-wide data integration
D. Elimination of cybersecurity risks
Explanation: Centralized enterprise databases improve data consistency, reduce duplication,
and facilitate organization-wide reporting.
3. During a software implementation, users continually request new features
after development has begun, delaying project completion. This situation is best
described as:
A. Risk transference
, B. Business continuity
C. Scope creep
D. Benchmarking
Explanation: Scope creep occurs when project requirements expand without corresponding
adjustments to schedule, budget, or resources.
4. Which project management constraint is most directly affected when
additional features are added without increasing the budget?
A. Organizational culture
B. Vendor selection
C. Project schedule
D. Regulatory compliance
Explanation: Additional work generally requires more time when financial resources remain
unchanged.
5. A project manager identifies a potential cybersecurity threat that has a low
probability but extremely high business impact. What is the most appropriate
first step?
A. Ignore the threat
B. Accept the risk automatically
C. Assess and document the risk before determining a response strategy
D. Purchase additional hardware immediately
Explanation: Risk management begins with identification and assessment before mitigation,
transfer, avoidance, or acceptance decisions.
6. Which document formally authorizes a project and grants authority to the
project manager?
A. Risk register
B. Work breakdown structure