Detailed Answers 100% Verified.
T/F If price is part of the final selection criteria and the price is the totla cost of construction is not 100%
the final and sole selection criteria, then delivery method is Best Value: Total Cost - correct answers
False
T/F Some industry participants use the term contract type to mean the basis of reimbursement and
others use the term to refer to the project delivery method. - correct answers True
T/F Basic philosophy of lean construction is centered on the idea of eliminating waste. - correct answers
True
Which Procurement option is defined as "competition where price is a factor in the final selection
criteria?" - correct answers Low Bid
What basis of reimbursement typically used with IPD? - correct answers Target Price or estimated
maximum price
Which procurement method is typically used when selecting an Agent Cm firm? - correct answers QBS
T/F Agency CM firms may coordinate, receive, and award trade bids and proposals for the owner. -
correct answers True
T/F Surety bonds such as payment bonds and performance bonds in the const. industry are considered
to be the same as insurance - correct answers False
T/F Case evaluation involves a neutral third party or facilitator that is not empowered to make a decision
on the dispute - correct answers True
, Which statement(s) are true regarding prequalifications? - correct answers -May be used in DBB
-May be used in DB
May be used when selecting designer/constructor
- One process for procurement, RFQ/RFP, has it built into the processs
-May be used with IPD
-May be used w/ CM at risk
T/F Lump Sum of Fixed Firm Price are generally open-book with the owner having access to the
contractor's or design-builder's cost related info - correct answers False
Which of the following services may be provided by an Agent CM firm? - correct answers - Locating
temp. facilities for project team members
- Identifying and facilitating long lead item orders
- Coordinate, receive and award trade bids and proposals
- Help Owner obtain permits and gov. approvals
- Help owner obtain consultants
T/F Once the response to the RFP have been received, the owner evaluates them using either a
formulaic approach for a trade-off analysis approach - correct answers True
which of the following is NOT an accelerated procurement approach? - correct answers Owner In-House
Contracting
T/F Target price is also known as no GMP - correct answers False
T/F Performance specs precisely state how work is to be performed, and describe in detail the materials
to be used and the manner in which work is to be executed. - correct answers False
Retainage usually amounts to what percentage of the contract price. - correct answers 5-10%