FDOT: Final Estimates - Level 1-Test Questions Fully Solved.

Document preview thumbnail
Preview 2 out of 5 pages

What two types of Estimates are needed to pay for the work performed by contractors? - Answer Final & Progress Monthly In case of discrepancies among the contract documents, which document takes the highest precedence? - Answer Special Provisions Contractors Receive progress payments on the basis of? - Answer Monthly Progress Estimates Which of the following sets forth the Department's methods and procedures for preparing and checking final estimates? - Answer Preparation and Documentation Manual (PDM) Which Document contains a series of Specially designed forms that show both original estimates of quantities and the final quantities as measured ad accepted? - Answer Computation Books Which Document contains alignment notes, cross-section notes, linear and area measurements and dimension sketches? - Answer Field Notebooks Where are major changes during construction documented and "as-built" conditions shown? - Answer Field Notebooks What identification is needed to show on the front cover of a field book? - Answer FEID, Contract number, General contents of the book When making corrections to a field book entry, you should: - Answer strike through, initial and enter correct data and date What should be started on the first lined page (page 1) of a field book? - Answer INDEX An entire page of a field notebook you are using is incorrect, what do you do to correct the situation? - Answer Mark the page VOID and reference it to a new page showing the correct information.

Content preview

FDOT: Final Estimates - Level 1-Test
Questions Fully Solved.
What two types of Estimates are needed to pay for the work performed by contractors? -
Answer Final & Progress Monthly



In case of discrepancies among the contract documents, which document takes the highest
precedence? - Answer Special Provisions



Contractors Receive progress payments on the basis of? - Answer Monthly Progress
Estimates



Which of the following sets forth the Department's methods and procedures for preparing and
checking final estimates? - Answer Preparation and Documentation Manual (PDM)



Which Document contains a series of Specially designed forms that show both original
estimates of quantities and the final quantities as measured ad accepted? - Answer
Computation Books



Which Document contains alignment notes, cross-section notes, linear and area measurements
and dimension sketches? - Answer Field Notebooks



Where are major changes during construction documented and "as-built" conditions shown? -
Answer Field Notebooks



What identification is needed to show on the front cover of a field book? - Answer FEID,
Contract number, General contents of the book



When making corrections to a field book entry, you should: - Answer strike through, initial
and enter correct data and date



What should be started on the first lined page (page 1) of a field book? - Answer INDEX



An entire page of a field notebook you are using is incorrect, what do you do to correct the
situation? - Answer Mark the page VOID and reference it to a new page showing the correct
information.

, "Check Levels" must be run at the start of a construction project to assure that: - Answer
Construction will be done to design elevations & final measurements for payment will be from
the same base elevations as the original survey.



What should accompany final measurements so that nonstandard measurements may be
interpreted accurately? - Answer Sketches



In the REMARKS column of most computation book forms a reference should be made to the: -
Answer Source Documents



When is it permissible to record only the net weight on an asphaltic concrete tabulation form? -
Answer Never, gross tare must be included also



A limerock base course is constructed in two 13-foot widths between station 19+40.20 and
station 84+50.00. What is the area of the base course to the whole square yard? - Answer
18,806 SY



How many square yards are in one acre? - Answer 4,840



Determine the area of the section (G) in the circle to the tenth of a square foot. (NOTE: A= pi
r(squared) x (angle/360degrees) - Answer 887.3 SF



If you have a benchmark at an elevation of 80.25' and a back sight rob reading of 5.45', what is
the height of instrument (HI)? - Answer 85.70'



If you have a pile cut off elevation of 50.00' and tip elevation of 10.00', what would your pile
length be? - Answer 40'



Where can you find the typical widths of base and surface courses? - Answer Typical Sections
sheets of the plans



Thirteen and one-half gallons is equal to how many cubic feet? - Answer 1.8 Cubic Feet



Using the data given below, find the volume to the nearest cubic yard. The areas were
determined for the cross sections at these stations:



Station: Area (Sq Feet):

5091+00 287.60

5091+38 302.0

Document information

Uploaded on
June 27, 2026
Number of pages
5
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
COCOSOLUTIONS
4.1
(39)
Sold
232
Followers
16
Items
9649
Last sold
1 day ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions