**Question 1.** Which of the following best describes the primary purpose of a building department’s
public information desk?
A) To approve construction plans
B) To collect permit fees
C) To provide accurate information on permit requirements and processes
D) To conduct field inspections
Answer: C
Explanation: The public information desk is tasked with answering inquiries about permits, fees, and
procedures, not with approving plans or conducting inspections.
**Question 2.** Under the Public Records Act, a citizen requests copies of all permit applications filed in
the last year. The department may:
A) Deny the request because the records are confidential.
B) Provide the records, redacting any personal identifying information.
C) Charge a flat fee of $500 for the entire request.
D) Only provide records for permits that were denied.
Answer: B
Explanation: Public records must be made available, but personal data such as Social Security numbers
must be redacted to protect privacy.
**Question 3.** When verifying a permit application for completeness, which item is NOT typically
required?
A) Owner’s legal name and address
B) Contractor’s current license number
C) Applicant’s favorite color
D) Site plan showing property lines
Answer: C
Explanation: Personal preferences like favorite color are irrelevant to permit processing.
**Question 4.** The calculation of a building permit fee is most directly based on:
, ICC Permit Technician Ultimate Exam
A) The number of pages in the construction documents
B) The estimated construction cost or valuation
C) The number of employees the contractor has
D) The distance of the site from the city hall
Answer: B
Explanation: Permit fees are generally proportional to the project’s valuation or construction cost.
**Question 5.** Which of the following is a legal requirement for the retention of inspection reports?
A) Keep them for at least 2 years after project completion.
B) Store them in a locked drawer for 5 years.
C) Retain them for a minimum of 5 years, unless a longer period is mandated by state law.
D) Destroy them once the certificate of occupancy is issued.
Answer: C
Explanation: Most jurisdictions require a minimum of five years retention, though some codes may
specify longer periods.
**Question 6.** Inter-departmental coordination is essential for plan review. Which department is most
likely to review fire protection provisions?
A) Health Department
B) Fire Marshal’s Office
C) Planning Department
D) Public Works
Answer: B
Explanation: The Fire Marshal’s Office evaluates fire suppression systems, egress, and fire resistance.
**Question 7.** A building official’s authority to issue a stop-work order is derived from:
A) The city’s zoning ordinance.
B) The police power granted to municipalities.
C) The contractor’s license agreement.
, ICC Permit Technician Ultimate Exam
D) The state’s corporate law.
Answer: B
Explanation: Police power allows local governments to protect health, safety, and welfare, including
issuing stop-work orders.
**Question 8.** The phrase “shall” in a building code indicates that the requirement is:
A) Optional, based on the official’s discretion.
B) Mandatory and enforceable.
C) Recommended but not required.
D) Subject to future amendment.
Answer: B
Explanation: “Shall” denotes a mandatory provision that must be complied with.
**Question 9.** Which document is required when a contractor submits “deferred submittals”?
A) A signed affidavit stating the submittals will be provided within 30 days of occupancy.
B) A revised construction schedule.
C) An additional permit fee.
D) No additional documentation is needed.
Answer: A
Explanation: Deferred submittals must be accompanied by a written commitment to submit the
documents within a specified timeframe.
**Question 10.** An occupancy classified as Group R-3 is most commonly associated with:
A) High-rise office buildings.
B) Single-family detached dwellings.
C) Small hotels.
D) Warehouses.
Answer: B
Explanation: Group R-3 covers one- and two-family dwellings, such as single-family homes.
, ICC Permit Technician Ultimate Exam
**Question 11.** Which construction type permits the use of non-combustible exterior walls with a
maximum fire-resistance rating of 1-hour?
A) Type I
B) Type II
C) Type III
D) Type V
Answer: C
Explanation: Type III construction allows non-combustible exterior walls with limited fire-resistance
ratings, while interior elements may be combustible.
**Question 12.** The term “grade plane” on a site plan refers to:
A) The elevation of the finished floor.
B) The natural ground level before any grading.
C) The height of the roof.
D) The depth of the basement.
Answer: B
Explanation: Grade plane is the existing ground surface prior to excavation or fill.
**Question 13.** A “mezzanine” is defined as:
A) A full-height floor extending the entire building footprint.
B) An intermediate level that does not extend over the entire floor area and is usually open to the floor
below.
C) A basement level below grade.
D) The roof deck of a building.
Answer: B
Explanation: Mezzanines are partial floors that do not cover the entire floor area and are often used for
storage or office space.
**Question 14.** In a zoning map, a “C-2” district most likely permits: