**Question 1. Which of the following best describes the authority of the Building Official regarding
special inspectors?**
A) The Building Official can only recommend inspectors but cannot approve them.
B) The Building Official has the authority to approve, suspend, or revoke a special inspector’s
qualifications.
C) The Building Official must defer all decisions to the Engineer of Record.
D) The Building Official can only stop work, not approve inspectors.
Answer: B
Explanation: Under ICC regulations, the Building Official is empowered to approve special inspectors and
may suspend or revoke that approval if performance is unsatisfactory.
**Question 2. The primary duty of a special inspector is to:**
A) Design structural elements.
B) Verify that construction conforms to approved plans and specifications.
C) Issue building permits.
D) Perform all field testing for the project.
Answer: B
Explanation: Special inspectors are tasked with observing construction and confirming compliance with
approved documents, not designing or permitting.
**Question 3. Which document must a contractor maintain on-site for the duration of the project?**
A) The original construction contract.
B) The approved set of plans and specifications.
C) The contractor’s insurance policy.
D) The subcontractor’s pay records.
Answer: B
Explanation: The ICC requires that the approved set of plans be kept on-site for reference by inspectors
and the Building Official.
**Question 4. In the Special Inspection Process, the Statement of Special Inspections (SSI) is:**
, ICC General Requirements Ultimate Exam
A) A contract amendment between owner and contractor.
B) A list of all required special inspections, their frequency, and acceptance criteria.
C) A safety plan for the construction site.
D) A warranty document for completed work.
Answer: B
Explanation: The SSI outlines each required special inspection, the method, frequency, and the
standards to be used.
**Question 5. Continuous inspection is defined as:**
A) An inspection performed only at the beginning of construction.
B) An inspection that occurs at regular, predetermined intervals regardless of work progress.
C) An inspection that is performed throughout the entire construction of a component, observing every
critical step.
D) An inspection that is performed only after the work is completed.
Answer: C
Explanation: Continuous inspection requires observation of each critical step of the construction activity
to ensure compliance.
**Question 6. Which of the following is a primary responsibility of the contractor when scheduling
inspections?**
A) To decide the inspection frequency without consulting the special inspector.
B) To notify the special inspector in writing at least 24 hours before the required inspection.
C) To perform the inspection themselves.
D) To delay inspections until after the project is complete.
Answer: B
Explanation: The contractor must provide timely notice to the inspector to allow coordination and
compliance with scheduling requirements.
**Question 7. When a non-conforming item is discovered, the special inspector must:**
A) Immediately stop all work on the project.
, ICC General Requirements Ultimate Exam
B) Issue a Non-Conformance Report (NCR) documenting the deviation and required corrective action.
C) Ignore it if the contractor claims it is minor.
D) Replace the item without consulting the Engineer of Record.
Answer: B
Explanation: The proper procedure is to issue an NCR, track the issue, and ensure corrective measures
are taken.
**Question 8. According to IBC Chapter 17, which material requires a special inspection for weld
quality?**
A) Reinforced concrete.
B) Structural steel.
C) Masonry units.
D) Engineered wood.
Answer: B
Explanation: IBC Chapter 17 mandates special inspection of steel welds to verify compliance with
applicable standards.
**Question 9. Which ASTM standard is commonly used for labeling concrete mix designs on-site?**
A) ASTM C150.
B) ASTM A615.
C) ASTM C33.
D) ASTM A992.
Answer: C
Explanation: ASTM C33 specifies concrete aggregates and is often referenced for mix design labeling.
**Question 10. The Engineer of Record is primarily responsible for:**
A) Issuing building permits.
B) Approving shop drawings and ensuring design intent is maintained.
C) Conducting daily safety inspections.
D) Managing the contractor’s payroll.
, ICC General Requirements Ultimate Exam
Answer: B
Explanation: The Engineer of Record reviews and approves shop drawings, confirming they align with
the original design intent.
**Question 11. Which of the following is NOT a typical content of a daily report prepared by a special
inspector?**
A) Weather conditions affecting the work.
B) Observations of work performed and any testing conducted.
C) The contractor’s payment schedule.
D) Any deviations from approved documents noted during the day.
Answer: C
Explanation: Daily reports focus on construction observations, testing, and non-conformances, not
financial matters.
**Question 12. Under ICC General Requirements, a special inspection agency must demonstrate:**
A) Ownership of the construction site.
B) That its staff hold the required qualifications and certifications for the inspections they perform.
C) That it can provide all construction labor.
D) That it has a minimum of ten years of experience in real estate sales.
Answer: B
Explanation: Agencies must prove that their inspectors are qualified per the code’s requirements.
**Question 13. In high-seismic regions, the IBC requires special inspection of which system?**
A) Roof drainage.
B) Fire alarm wiring.
C) Seismic-resistant structural elements.
D) Interior paint finishes.
Answer: C
Explanation: Seismic-resistant systems must be inspected to verify compliance with seismic design
criteria.