Control chart - correct answer ✔Which quality control tool should be used to monitor the current
status or end result of a process?
Technical tools
and
People involvement. - correct answer ✔What are two important aspects of Six Sigma?
Capacity utilization - correct answer ✔Which capacity planning measurement tells how much capacity
a company is using?
An effective capacity is lower than design capacity.
and
An effective capacity is a permanent measure used to achieve design capacity. - correct answer
✔Which two statements are true about effective capacity?
Line Process
and
Continuous process - correct answer ✔Which two types of operations include repetitive processes?
Throughput time/value-added time - correct answer ✔Which formula would compute process
velocity?