Why should reviews be To check the project is on track, spot
conducted throughout the deviations and emerging risks early,
project life cycle? evaluate positive/negative outcomes
at each stage, and gain an
independent perspective so key
details aren't overlooked.
What is the purpose of a To review viability of the project
decision gate review? work against the business case and
the PMP, and decide whether the
project should proceed to the next
phase.
When do decision gate reviews At the end of a phase of work (e.g.,
typically happen? concept, definition, deployment),
often aligned to governance and
funding decisions.
How do decision gate reviews Time-bound gate reviews may
work in an iterative life cycle? happen at the end of each timebox
so agreed changes can be
incorporated into the next timebox.
What are the main benefits of They create structured control;
decision gate reviews? check progress and benefits are on
track; build trust between PM and
sponsor; provide documented
Questions and Answers with Verified
Solutions | Latest Updated 2026
Why should reviews be To check the project is on track, spot
conducted throughout the deviations and emerging risks early,
project life cycle? evaluate positive/negative outcomes
at each stage, and gain an
independent perspective so key
details aren't overlooked.
What is the purpose of a To review viability of the project
decision gate review? work against the business case and
the PMP, and decide whether the
project should proceed to the next
phase.
When do decision gate reviews At the end of a phase of work (e.g.,
typically happen? concept, definition, deployment),
often aligned to governance and
funding decisions.
How do decision gate reviews Time-bound gate reviews may
work in an iterative life cycle? happen at the end of each timebox
so agreed changes can be
incorporated into the next timebox.
What are the main benefits of They create structured control;
decision gate reviews? check progress and benefits are on
track; build trust between PM and
sponsor; provide documented