Answer | Ultimate Prep Bundle |
A+ Verified
• The contractors team member who directs, manages and coordinates
the day-to-day project activities of the contractor's staff, suppliers and
subcontractors is: -✓✓Superintendent
• Activities that constitute the project include all of the following
EXCEPT: -✓✓a. Constructing the facility
b. Managing the completed facility
c. Procuring materials, labor and equipment for construction
d. Designing the facility
(B) Managing the completed facility
• UniFormat organizes information based upon: -✓✓Physical parts of a
facility called functional elements
• The CSI Uniform Drawing System (UDS): -✓✓Establishes drawing
set content and order
• The contract documents come with what type of warranty under the
Spearin Doctrine? -✓✓Implied warranty
• A project's sustainable design requirements may be based upon: -✓✓a.
Owner driven initiatives
b. Utility rebate programs
c. Local or state regulations
d. All of the above
(D) All of the above
, • Who is responsible for purchase and maintenance of insurance
protecting the owner against loss of use of the owner's property or
disruption of normal operations under A201? -✓✓Owner
• Which of the five listed consecutive steps in the programming process
are MISSING from the list below:
1. Establish goals
2. Collect and analyze facts
3. Uncover and test concepts
4. State the problem -✓✓Determine needs
• The PDPG defines the goal of the project delivery team as consisting
of the following EXCEPT: -✓✓a. Meet the owner's requirements
b. Meet the designer's sustainability goals
c. Be completed on time
d. Be completed within the owner's budget
(B) Meet the designer's sustainability goals
• The PDPG quotes the Whole Building Design Guide as defining
project cost effectiveness as including the following:
1. The lowest first-cost structure that meets the program
2. The design with the lowest operating and maintenance cost
3. The design that incorporates construction teams preferred products
and processes
4. The facility in which users are most productive -✓✓. 1, 2, 4
• The practice of all parties involved in the project contractually waiving
all claims against one another to the extent they are insured is referred to
as: -✓✓Waiver of Subrogation