1.
In construction specifications, which document primarily establishes
administrative requirements for the project?
A. Technical Specifications
B. Division 01 General Requirements
C. Drawings
D. Addenda
Answer: B. Division 01 General Requirements ✔
*Rationale: Division 01 defines administrative procedures, including submittals,
quality control, and project coordination requirements.
2.
What is the primary purpose of a submittal during construction?
A. To replace contract documents
B. To verify compliance with design intent
C. To determine project financing
D. To approve contractor payment schedule
,Answer: B. Verify compliance with design intent ✔
*Rationale: Submittals ensure materials and systems meet specified
requirements before installation.
3.
Which organization publishes MasterFormat?
A. ASTM International
B. CSI (Construction Specifications Institute)
C. AIA
D. OSHA
Answer: B. CSI (Construction Specifications Institute) ✔
*Rationale: CSI develops MasterFormat, the standardized system for organizing
construction information.
4.
A performance specification primarily describes:
A. Exact materials and brands
B. Contractor labor rates
C. Required outcomes and performance criteria
D. Project scheduling requirements
Answer: C. Required outcomes and performance criteria ✔
*Rationale: Performance specs define results, not specific materials or methods.
5.
Which contract delivery method involves a single entity responsible for design and
construction?
,A. Design-Bid-Build
B. Construction Management at Risk
C. Design-Build
D. Lump Sum Contract
Answer: C. Design-Build ✔
*Rationale: Design-Build integrates design and construction responsibility under
one contract.
6.
What is the primary function of an addendum?
A. Modify contract documents after bidding
B. Approve construction payments
C. Replace specifications entirely
D. Finalize project completion
Answer: A. Modify contract documents after bidding ✔
*Rationale: Addenda are issued during bidding to clarify or modify documents.
7.
Which document governs quality control procedures on site?
A. Division 01
B. Bid Form
C. Drawings
D. Owner’s Manual
Answer: A. Division 01 ✔
*Rationale: Quality control and assurance requirements are typically defined in
Division 01.
, 8.
What does “Basis of Design” refer to?
A. Contractor pricing structure
B. Engineer’s design assumptions and criteria
C. Legal contract terms
D. Construction schedule baseline
Answer: B. Engineer’s design assumptions and criteria ✔
*Rationale: BOD documents the technical assumptions and design standards
used.
9.
Which type of specification allows the most contractor flexibility?
A. Prescriptive specification
B. Closed specification
C. Performance specification
D. Proprietary specification
Answer: C. Performance specification ✔
*Rationale: Performance specs define outcomes rather than methods, allowing
flexibility.
10.
RFIs are primarily used to:
A. Request payment approval
B. Clarify design or specification issues
C. Replace shop drawings
D. Approve subcontractors