Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 34 pages
Exam (elaborations)

CM 310: FINAL FINAL UPDATED ACTUAL Questions and CORRECT Answers

Document preview thumbnail
Preview 4 out of 34 pages

CM 310: FINAL FINAL UPDATED ACTUAL Questions and CORRECT Answers

Content preview

CM 310: FINAL FINAL UPDATED ACTUAL
Questions and CORRECT Answers
Project - CORRECT ANSWER unique, temporary

Sustainable project - CORRECT ANSWER balance--> social, economic, environmental

Project participants - CORRECT ANSWER project owners/end users, design firm, construction firm

Pillars of Success + Foundations - CORRECT ANSWER Cost, Safety, Quality, Time

- Document Control, Communication, Organization, Coordination

Project Phases - CORRECT ANSWER Planning, Design, Construction, Operations

Planning Phase - CORRECT ANSWER realize a need, perform analysis

Design - CORRECT ANSWER schematic design --> drawings, estimate

Subsection: design development

Design Development - CORRECT ANSWER construction documents

Construction - CORRECT ANSWER Planning + Start-Up, Execution, Control/Admin, Close-out

Pre-Construction Activities - CORRECT ANSWER selecting subs, estimates, review of construction documents

Build to Use - CORRECT ANSWER Use and Retain
- builds and owns facility

e.g. Custom House

Build to Lease - CORRECT ANSWER Lease and Retain
- retain ownership, leases out use

e.g. Strip Mall

Build to Sell - CORRECT ANSWER Lease and Transfer
- transfer ownership, lease out use

e.g. Residential Developer

Sell to Lease - CORRECT ANSWER RARE
- transfer ownership, personally lease out

If owner needs to cash out on equity, then rent facility

General Contractor - CORRECT ANSWER Planning, coordination.
Generalist.
Self-performs some work, subs out the rest

Construction Manager - CORRECT ANSWER Like general contractor, doesn't self-perform work

Heavy-Civil Contractor - CORRECT ANSWER Self-performs most tasks

Agency Construction Manager - CORRECT ANSWER coordinate with subs that contract directly with owner

assist project owners as consultants

,An out-of-house owner's representatives

AHJ - CORRECT ANSWER Authority having Jurisdiction

e.g. inspectors, enforcers of code

Insurance Companies - CORRECT ANSWER analyze, establish premium price to assume designer/general
contractor liability

Construction Sureties - CORRECT ANSWER analyze, decide if risk low enough to issue bond

Bid Bond - CORRECT ANSWER assures the owner that contractor is submitting price proposal that is accurate

Performance bond - CORRECT ANSWER protects owner if general contractor is unable to fulfill contractual
obligations

a promise to fulfill contractual obligations

Payment bond - CORRECT ANSWER assures owner that general contractor will pay subcontractor, direct labor,
material supplies

Owner's Representative - CORRECT ANSWER in-house representation/decision-making owner's behalf

Designer of Record - CORRECT ANSWER submits building permit request

Lead Designer - CORRECT ANSWER Overseer/Manager of design staff

Journey-Level Craftsmen - CORRECT ANSWER fully qualified, experienced workers in their staff

Obligee - CORRECT ANSWER Project Owner

asks that principle submit bond

Principle - CORRECT ANSWER General Contractor

requests that surety issue bond to obligee on their beaf

Surety - CORRECT ANSWER Bonding Company

issues bond to obligee on principle's behalf

Design-Bid-Build - CORRECT ANSWER designer awarded contract BEFORE design complete

GC awarded contract AFTER design complete

Construction Manager at Risk - CORRECT ANSWER designer awarded contract BEFORE design complete

GC awarded contract AFTER design is 60%-90% complete

Similar to Agency CM, but legally like a contractor

Progressive Design-Build - CORRECT ANSWER Designer and GC contracted together after design is 60%-90%

Two-step contracting process

Competitive Design-Build - CORRECT ANSWER Designer and GC contracted together after design is 10%-30%
complete

,Early designs are bid out to be completed by other design constultants

Bridging Design-Build - CORRECT ANSWER Designer and GC contracted together after design is 80%-100%
complete

Designs constitute basis of contract

Integrated Project Delivery - CORRECT ANSWER one, multi-player contractual agreement

Project Delivery - CORRECT ANSWER act of achieving project objectives

Procurement - CORRECT ANSWER act of purchasing external services and materials

Contracting - CORRECT ANSWER establishing contract of services and materials

Force Account - CORRECT ANSWER owner self-performs a scope

Multi-Prime Contracting - CORRECT ANSWER self-performs GC coordination role

Procurement Selection Methods - CORRECT ANSWER - competitive bidding selection
- best value selection
- qualification-based selection
- sole-source selection

Competitive bidding selection - CORRECT ANSWER Low Price. DBB.

A+B Bidding--> A=cost; B=time

Sometimes requires pre-qualifications to bid (ensure that GC qualifies) or bond purchase (sureties only sell to reliable
GC)

Prevalent in public firms.

Popular due to simplicity.

Quality of design package makes or breaks the effectiveness. Also, differing site conditions.

Often incorporates value engineering (VE) change proposals

Best Value Selection - CORRECT ANSWER Multi-criteria. Any PDM.

Usually RFP-->RFQ

Qualification-based Selection - CORRECT ANSWER Multi-criteria. De-emphasizes price.

Sole-Source Selection - CORRECT ANSWER GC selected because only they are capable. Non-Competitive.

Contractual relationship with designer - CORRECT ANSWER trust-based

Contractual relationship with contractor - CORRECT ANSWER arm's length

Three types of contracts - CORRECT ANSWER prime contracts, subcontracts, other contracts

Prime Contract - CORRECT ANSWER agreement between owner + other party

defines rights/obligations of each signatory party

Private owners tend to negotiate contracts more
Public owners rarely negotiate anything that may have affected selection

, Subcontract - CORRECT ANSWER contract following prime contracts, does not involve owner

defines rights/obligations of each signatory party

mirrors details of prime contract to streamline process

Other contracts - CORRECT ANSWER e.g. joint venture bw subs

Contractual agreement - CORRECT ANSWER main document

Incorporation of reference - CORRECT ANSWER incorporates other contractual documents to contractual
agreement

General conditions - CORRECT ANSWER describes operating procedures used on all owner's projects of similar
type

Special conditions - CORRECT ANSWER describes operating procedures unique to the requirements for the
project

Construction drawings - CORRECT ANSWER graphical description of project, including geometrical information
and materials

Construction specification - CORRECT ANSWER textual description of project, includes:

- additional material info
- quality acceptance processes
- other performance expectations

Organized by CSI MasterFormat

Who - CORRECT ANSWER signatory contractual parties, any relationships to other parties

What - CORRECT ANSWER work to be performed

Where - CORRECT ANSWER location of project

How much - CORRECT ANSWER pricing method, including contact price (if known)

process to evaluate reimbursement cost

fees to be awarded

How to get paid - CORRECT ANSWER payment method, processes to obtain progress/final payments

Other hows - CORRECT ANSWER contract administration:
- changes to contract
- disputes
- unforseen circumstances
- design flaws
- contract termination

Standard contracts - CORRECT ANSWER can be adapted to a specific project by filling in the blanks

Include:
- AIA Contracts (American Institute of Architects)
- ConsensusDocs
- NAHB Contracts (National Association of Home Builders): Residential
- Engineers Joint Contract Documents Committee (EJCDC) Contract Documents

Document information

Uploaded on
June 17, 2026
Number of pages
34
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES
4.0
(230)
Sold
1512
Followers
106
Items
107180
Last sold
2 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions