WGU C268 Spreadsheets (2026/2027) |
Latest Exam-Based Tasks | 100% Verified
Answers | Exam Prep Guide | A+
• Calculate, in cell D20, the interest amount for period 1 by multiplying
the balance in period 0 (cell F19) by the loan interest rate (cell C13)
divided by 12. Dividing the interest rate by 12 results in the monthly
interest rate. This formula is reusable. The interest for a given period is
always the monthly interest rate times the balance from the previous
period. -✓✓=F19*$C$13/12
• Calculate, in cell E20, the principal amount for period 1. The principal
amount is the difference between the payment amount (cell C20) and
the interest amount (cell D20) for period 1. Construct your formula in
such a way that it can be reused to complete the "principal" column of
the amortization table. -✓✓=C20-D20
• Calculate, in cell F20, the balance for period 1. The balance is the
difference between the balance for period 0 (cell F19) and the principal
amount for period 1 (cell E20). This formula is reusable. The balance is
always calculated as the difference between the balance from the
previous period and the principal amount for the current period. -
✓✓=F19-E20
• Calculate, in cell G12, the total amount paid by multiplying the
payment amount (cell C15) by the term of the loan (cell C12). -
✓✓=C15*C12
,• Calculate the total interest paid in cell G13. The total interest paid is
the sum of all interest paid in the "Interest" column of the amortization
table. -✓✓=SUM(D20:D67)
• Check to see if the total interest calculation in the amortization table
is correct. The total interest paid is also equal to the difference
between the total amount paid over the course of the loan and the
original loan amount. Insert a formula into cell G14 to calculate the
difference between the total amount paid and the original loan
amount. Notice the negative sign associated with the original loan
amount. This value should equal the total interest calculated using the
amortization table. -✓✓=G12-ABS(C11)
• Assume you have made the first 36 payments on your loan. You want
to trade the car in for a new car. You believe that you can sell your car
for $4000. Will this cover the balance remaining on the car in period
36? Answer either "Yes" or "No" in cell G15 from the drop-down menu.
-✓✓No
• Use the HLOOKUP function to complete the "Hourly Wage" column of
table 1. Use the "Employee" column of table 1 as the lookup_value and
the "Employee Wage Information" above table 1 as your reference
table. -✓✓=HLOOKUP(D16,$E$11:$H$12,2,FALSE)
, • Use the AND function to complete the "Time Bonus?" column of table
1. An employee earns a time bonus if the project's "Hours Worked" are
fewer than the "Estimated Hours" and if the work "Quality" is greater
than 1. -✓✓=AND(E16<C16,H16>1)
• Use the OR function to complete the "Outcome Bonus?" column of
table 1. An employee earns an outcome bonus if the difficulty of a job is
greater than 3 or if the quality of their work is equal to 3. -
✓✓=OR(G16>3,H16=3)
• Use the IF function to complete the "Time Bonus $" column of table 1.
If an employee earns a time bonus (i.e., the corresponding cell in the
"Time Bonus?" column is TRUE), then "Time Bonus $" is the "Job Pay"
for that project times the bonus percentage in cell M11. Otherwise
"Time Bonus $" is 0. -✓✓=IF(I16,K16*$M$11,0)
• Use the IF function to complete the "Outcome Bonus $" column of
table 1. If an employee earns an outcome bonus (i.e., the
corresponding cell in the "Outcome Bonus?" column is TRUE), then
"Outcome Bonus $" is the "Job Pay" for that project times the outcome
bonus percentage in cell M12; otherwise, "Outcome Bonus $" is 0. -
✓✓=IF(J16,K16*$M$12,0)
• Use the IF function to complete the "Comments" column of table 1.
Display "Good Job" if both the "Hours Worked" are less than or equal to
the "Estimated Hours" for a project and the assessed "Quality" of that
project is greater than 1. Display "Too Much Time" if the "Hours
Latest Exam-Based Tasks | 100% Verified
Answers | Exam Prep Guide | A+
• Calculate, in cell D20, the interest amount for period 1 by multiplying
the balance in period 0 (cell F19) by the loan interest rate (cell C13)
divided by 12. Dividing the interest rate by 12 results in the monthly
interest rate. This formula is reusable. The interest for a given period is
always the monthly interest rate times the balance from the previous
period. -✓✓=F19*$C$13/12
• Calculate, in cell E20, the principal amount for period 1. The principal
amount is the difference between the payment amount (cell C20) and
the interest amount (cell D20) for period 1. Construct your formula in
such a way that it can be reused to complete the "principal" column of
the amortization table. -✓✓=C20-D20
• Calculate, in cell F20, the balance for period 1. The balance is the
difference between the balance for period 0 (cell F19) and the principal
amount for period 1 (cell E20). This formula is reusable. The balance is
always calculated as the difference between the balance from the
previous period and the principal amount for the current period. -
✓✓=F19-E20
• Calculate, in cell G12, the total amount paid by multiplying the
payment amount (cell C15) by the term of the loan (cell C12). -
✓✓=C15*C12
,• Calculate the total interest paid in cell G13. The total interest paid is
the sum of all interest paid in the "Interest" column of the amortization
table. -✓✓=SUM(D20:D67)
• Check to see if the total interest calculation in the amortization table
is correct. The total interest paid is also equal to the difference
between the total amount paid over the course of the loan and the
original loan amount. Insert a formula into cell G14 to calculate the
difference between the total amount paid and the original loan
amount. Notice the negative sign associated with the original loan
amount. This value should equal the total interest calculated using the
amortization table. -✓✓=G12-ABS(C11)
• Assume you have made the first 36 payments on your loan. You want
to trade the car in for a new car. You believe that you can sell your car
for $4000. Will this cover the balance remaining on the car in period
36? Answer either "Yes" or "No" in cell G15 from the drop-down menu.
-✓✓No
• Use the HLOOKUP function to complete the "Hourly Wage" column of
table 1. Use the "Employee" column of table 1 as the lookup_value and
the "Employee Wage Information" above table 1 as your reference
table. -✓✓=HLOOKUP(D16,$E$11:$H$12,2,FALSE)
, • Use the AND function to complete the "Time Bonus?" column of table
1. An employee earns a time bonus if the project's "Hours Worked" are
fewer than the "Estimated Hours" and if the work "Quality" is greater
than 1. -✓✓=AND(E16<C16,H16>1)
• Use the OR function to complete the "Outcome Bonus?" column of
table 1. An employee earns an outcome bonus if the difficulty of a job is
greater than 3 or if the quality of their work is equal to 3. -
✓✓=OR(G16>3,H16=3)
• Use the IF function to complete the "Time Bonus $" column of table 1.
If an employee earns a time bonus (i.e., the corresponding cell in the
"Time Bonus?" column is TRUE), then "Time Bonus $" is the "Job Pay"
for that project times the bonus percentage in cell M11. Otherwise
"Time Bonus $" is 0. -✓✓=IF(I16,K16*$M$11,0)
• Use the IF function to complete the "Outcome Bonus $" column of
table 1. If an employee earns an outcome bonus (i.e., the
corresponding cell in the "Outcome Bonus?" column is TRUE), then
"Outcome Bonus $" is the "Job Pay" for that project times the outcome
bonus percentage in cell M12; otherwise, "Outcome Bonus $" is 0. -
✓✓=IF(J16,K16*$M$12,0)
• Use the IF function to complete the "Comments" column of table 1.
Display "Good Job" if both the "Hours Worked" are less than or equal to
the "Estimated Hours" for a project and the assessed "Quality" of that
project is greater than 1. Display "Too Much Time" if the "Hours