update technology - ✔✔what is not one of the fundamental steps that is included in the
project control cycle?
both A and B: information, good reporting system - ✔✔what is the essential(s) of an effective
project control system?
requests for information - ✔✔what is not an example of a source where you might gather field
information needed to develop your project controls?
all of the above: weather, defective material, overcrowded job sites - ✔✔what is an example of
a factor that can impact project performance?
it is usually negotiated into the construction contract when there is suspicion that some pricing
component of the estimate is in a high state of flux - ✔✔what is an escalation clause?
estimating productivity - ✔✔what is the riskiest element of the project control and project
planning?
to compress the overall schedule by accelerating certain activities within it so that they finish
sooner - ✔✔what does it mean to crash the schedule?
to predict the final cost and schedule outcomes on a project while the work is still in progress -
✔✔what does it mean to forecast in project management?
quality, cost, time - ✔✔what are the three primary tracking elements when monitoring project
performance?
update technology - ✔✔what is not one of the fundamental steps that is included in the
project control cycle?
both A and B: information, good reporting system - ✔✔what is the essential(s) of an effective
project control system?
requests for information - ✔✔what is not an example of a source where you might gather field
information needed to develop your project controls?
all of the above: weather, defective material, overcrowded job sites - ✔✔what is an example of
a factor that can impact project performance?
it is usually negotiated into the construction contract when there is suspicion that some pricing
component of the estimate is in a high state of flux - ✔✔what is an escalation clause?
estimating productivity - ✔✔what is the riskiest element of the project control and project
planning?
to compress the overall schedule by accelerating certain activities within it so that they finish
sooner - ✔✔what does it mean to crash the schedule?
to predict the final cost and schedule outcomes on a project while the work is still in progress -
✔✔what does it mean to forecast in project management?
quality, cost, time - ✔✔what are the three primary tracking elements when monitoring project
performance?