• 1. commissioning starts at the inception of a building project during the pre-design
phase, and continues through the post-acceptance phase.
2. provides an opportunity to cultivate a quality management focus among all design
and construction team members as they become involved with the project -
✓✓Comprehensive Commissioning
• Chapter 5 -✓✓Which Chapter of the ACG guideline identifies detailed methodology for
Comprehensive HVAC Commissioning?
• Pre-design
Design
Construction
Acceptance
Post Acceptance -✓✓What are the Comprehensive Commissioning phases?
• 1. Commissioning established as integral part of project
2. The owner selects the commissioning authority
3. Develop the scope of commissioning
4. Commissioning authority reviews design intent document -✓✓Comprehensive
Commissioning: Pre-design phase
• 1. Review design to ensure it accommodates commissioning
2. Write commissioning specifications defining contractor
responsibilities
3. Commissioning authority writes the commissioning plan
4. Establish the project schedule -✓✓Comprehensive Commissioning Design phase
• 1. Commissioning authority reviews contractor submittals
2. Commissioning authority updates commissioning plan
3. Commissioning process is coordinated—through project
schedule, commissioning plan and commissioning plan
and commissioning meetings
4. Carry out and document system verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents TAB work -✓✓Comprehensive
Commissioning Construction phase
• 1. Carry out FPTs on all HVAC systems
VERIFIED ANSWERS 2026 | Practice
Test | A+
• 1. commissioning starts at the inception of a building project during the pre-design
phase, and continues through the post-acceptance phase.
2. provides an opportunity to cultivate a quality management focus among all design
and construction team members as they become involved with the project -
✓✓Comprehensive Commissioning
• Chapter 5 -✓✓Which Chapter of the ACG guideline identifies detailed methodology for
Comprehensive HVAC Commissioning?
• Pre-design
Design
Construction
Acceptance
Post Acceptance -✓✓What are the Comprehensive Commissioning phases?
• 1. Commissioning established as integral part of project
2. The owner selects the commissioning authority
3. Develop the scope of commissioning
4. Commissioning authority reviews design intent document -✓✓Comprehensive
Commissioning: Pre-design phase
• 1. Review design to ensure it accommodates commissioning
2. Write commissioning specifications defining contractor
responsibilities
3. Commissioning authority writes the commissioning plan
4. Establish the project schedule -✓✓Comprehensive Commissioning Design phase
• 1. Commissioning authority reviews contractor submittals
2. Commissioning authority updates commissioning plan
3. Commissioning process is coordinated—through project
schedule, commissioning plan and commissioning plan
and commissioning meetings
4. Carry out and document system verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents TAB work -✓✓Comprehensive
Commissioning Construction phase
• 1. Carry out FPTs on all HVAC systems