and answers rated A+ 2026
D) Economies of Scope - correct answer ✔The ability to rapidly and inexpensively switch production
from one product to another enables what are sometimes referred to as:
A) Intermediate range - correct answer ✔Capacity planning that involves hiring, layoffs, some new
tooling, minor equipment purchases, and subcontracting is considered as which one of the following
planning horizons?
B) Longe-range - correct answer ✔Capacity planning involving acquisition or disposal of fixed assets
such as buildings, equipment or facilities is considered as which one of the following planning horizons?
A) 0.75
300 units of output divided by 400 units best operating level - correct answer ✔If the best operating
level of a piece of equipment is at a rate of 400 units per hour and the actual output during an hour is
300 units, which of the following is the capacity utilization rate?
C) 1.25
500 units of output divided by 400 units best operating level - correct answer ✔If the actual output of
a piece of equipment during an hour is 500 units and it's best operating level is at a rate of 400 units per
hour, which of the following is the capacity utilization rate?
B) 100 units per hour - correct answer ✔If the best operating level of a piece of equipment is at a rate
of 400 units per hour and the actual output during an hour is 300 units, which of the following is the
capacity cushion?
B) Pant within a plant (PWP) - correct answer ✔The capacity focus concept can be put into practice
through a mechanism called which of the following?