Exam coverage:-
New Mexico GF‑8 exam domains: Licensing & NMAC 14.10.5 scope,
transmission tower foundations (drilled piers, anchor bolts), storage
tanks (API 650/620, dikes, hydrostatic tests), substation site work & steel
erection, piping (ASME B31.1/B31.3, welding), safety (OSHA 1926
Subpart P, confined space, silica), environmental compliance (SPCC,
SWPPP), equipment (concrete slump, torque wrenches).
Section 1: Licensing, Business & New Mexico Regulations (Questions 1–
25)
Question 1
A contractor in New Mexico plans to build a new substation foundation
and install a 500,000‑gallon water storage tank for a power plant. Which
GF license classification is required for this non‑electrical infrastructure
work?
A) GA – General Building
B) GF‑8 – Transmission Lines, Tanks and Substations (Non‑Electrical)
C) EL‑1 – Electrical Distribution Systems
D) GF‑6 – Heavy Equipment Installation
Correct Answer: B
, Page 2 of 108
Rationale: The New Mexico GF‑8 classification specifically allows
contractors to “build, construct and place lines for the transmission or
conveyance of natural gas, petroleum, or petroleum products, tanks,
towers, pipelines, and any other similar type of construction, excluding
the installation of transformers, substation electrical components, and
other electrical connections”.
Question 2
Under N.M. Admin. Code § 14.6.6.8, which statement best describes the
scope of a contractor holding a GF‑8 license?
A) The licensee may perform major electrical work on substations.
B) The licensee may perform non‑electrical structural work, including the
assembly and installation of transmission towers, tank foundations, and
pipelines.
C) The licensee is restricted to residential construction only.
D) The licensee may replace transformers and switchgear as part of their
regular duties.
Correct Answer: B
Rationale: GF‑8 covers the non‑electrical structural components of
transmission lines, tanks, and substations.
Question 3
What is the primary purpose of N.M. Admin. Code § 14.10.5 (Minimum
Standards for Electrical Distribution and Transmission Facilities)?
A) To establish color codes for transmission towers.
B) To set minimum crew size for high‑voltage work.
, Page 3 of 108
C) To establish minimum standards for construction work on all
customer‑owned electrical distribution and transmission facilities in
New Mexico.
D) To define the maximum height of transmission towers.
Correct Answer: C
Rationale: This rule provides safety and construction standards for
transmission and distribution infrastructure, with which GF‑8
contractors must comply.
Question 4
Under N.M. Admin. Code § 14.10.5, who is ultimately responsible for
ensuring that a transmission line or tank installation project meets all
safety and construction standards?
A) The property owner.
B) The licensed contractor of record.
C) The equipment manufacturer.
D) The local utility provider.
Correct Answer: B
Rationale: The rule states that the “owner or operator of the transmission
and distribution facility must ensure” compliance, which in practice is
delegated to the licensed contractor performing the work.
Question 5
, Page 4 of 108
A contractor in New Mexico holds a valid GF‑8 license and is asked to
install a new 10,000‑gallon fuel storage tank at a rural substation. The
tank requires electrical connections for a level‑sensing system. May the
contractor perform the electrical hookup under the GF‑8 classification?
A) Yes, because GF‑8 allows all site work.
B) No, the electrical connections must be performed by a properly
licensed electrical contractor (e.g., EE‑98 or EL‑1).
C) Yes, as long as the voltage is below 50 volts.
D) No, unless the contractor obtains a separate EL‑1 endorsement.
Correct Answer: B
Rationale: GF‑8 explicitly excludes electrical installation of transformers,
substation electrical components, and other electrical connections,
which must be done by an electrical contractor.
Question 6
A GF‑8 contractor is preparing a bid for a new natural gas transmission
pipeline. Under NMAC 14.10.5, which of the following is a required
component of the construction plan for the pipeline?
A) Aesthetic finish requirements.
B) A clear description of safety and construction standards to be
followed, including dust control and erosion mitigation measures.
C) A marketing brochure for the project.
D) A list of potential subcontractors.
Correct Answer: B