Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 2 out of 10 pages
Exam (elaborations)

MAN 4583 EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026

Document preview thumbnail
Preview 2 out of 10 pages

MAN 4583 EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026 If you are estimating costs based upon historical data from experience with a comparable project, you are using: PERT estimating Analogous estimating Rough estimating Parametric estimating - Answers analogous To find the_____ activities with zero slack, you must calculate the forward and backward pass through your network. Predecessor Milestone Successor Critical path - Answers critical path In your network diagram, A is a predecessor for B, C, and D. Therefore, A is a _____ activity. Parallel Burst Milestone Merge - Answers burst To find the free slack (float) for each activity in your network diagram, you should calculate: Early start-late start Late start - early start Early finish - late finish Late finish - early start - Answers late start- early start Your network diagram includes all the following EXCEPT: Early start and early finish days Calendar dates Arrows showing precedence and flow. Late tart and late finish days - Answers calendar dates Scaling with a unit of measure, such as square feet or lines of code, is estimating. Analogous Parametric Top down Three-point - Answers parametric The _ in your budget is set aside for "unknown unknown" risks. Activity cost estimate Cost-baseline Contingency reserve Management reserve - Answers management reserve The helps cash flow planning and is the basis of controlling project costs & schedule once work commences. Work breakdown structure Gantt chart schedule Time phased budget Network diagram - Answers time phased budget An agile approach would work best in all the following situations except: Highly defines scope & requirements. High level of uncertainty in the market Developing iterations of the deliverable is ideal for the customer. High degree of risk - Answers highly defined scope and requirements Monitoring scrum project progress can be accomplished by using: Backlog grooming Burndown charts EVM performance reports Sprint iterations - Answers burndown charts The impediments in scrum supports the team by facilitating daily standups and removing Product owner Scrum master Developer Quality assurance - Answers scrum master Which of the following closing tasks occurs first? Close contracts Send invoice to customer. Obtain customer acceptance. Create closeout report. - Answers obtain customer acceptance Ideally, lessons learned should be collected: At the end of the execution phase At the end of the project only Following completion of every deliverable Throughout the project - Answers throughout the project In a bidding process, giving information to one vendor but not others are an ethical issue related to this pillar: Honesty Responsibility Fairness Respect - Answers fairness At the end of Week 2, AP "A" is 50% complete and its actual cost is 5. What is the cost variance of this activity? Ac: 5 a. 3 b -1 C. 1 d.-3 - Answers -3 ( EV- AC) The development team has encountered a problem with a software feature. They need to handle this problem quickly, but they can't make a face-to-face brainstorming session because they aren't local. Which alternative solution is best? videoconferencing conference call online chat session email - Answers videoconferencing One risk to your schedule is that a hard drive with customized software fails and you lose the work that was done. Resources on the project team regularly back up their work so they can resume work quickly after a hard drive failure. What type of risk management strategy do backups represent? risk avoidance risk mitigation risk transfer risk acceptance - Answers risk mitigation You have created a risk management plan for your project. Which type of response would you use if the scope was changed to remove a risky section of the project? transference mitigation avoidance acceptance - Answers avoidance Izzy has finished identifying risks for her big project, but is unsure how to account for unknown risks from a time and cost perspective. What is the general practice most companies use for projects? Set aside 20 percent of the budget and project duration. Set aside a percentage of the budget and project duration based on past projects. If you don't have past experience, use 15%. Set aside 25 percent of the budget or Project duration, or the highest percentage possible. Set aside 5 percent of the budget and project duration, or the lowest percentage possible. - Answers b. set aside a percentage of the budget and project duration based on past projects, if you dont have past experience use 15% Madhukant's project includes testing software functions. Which part of the quality management plan would address the processes that will be used to ensure the software is meeting the standards? quality control continuous improvement plan quality assurance plan quality standards for deliverables - Answers c. quality assurance plan Your boss is asking you to take on a reengineering project. The company hasn't run reengineering projects before, but has hired several project managers with reengineering experience. Which technique is best to use in this situation to estimate time and cost? bottom-up estimating top-down estimating parametric model Delphi technique - Answers delphi technique Turkan is developing a resource management plan for his project. Which part of this plan articulates who makes decisions, who performs work, and who needs to receive status on the project? the project organization chart the skills matrix the detailed staffing plan responsibility matrix - Answers responsibility matrix

Content preview

MAN 4583 EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026


If you are estimating costs based upon historical data from experience with a comparable project, you
are using:

PERT estimating
Analogous estimating
Rough estimating
Parametric estimating - Answers analogous
To find the_____
activities with zero slack, you must calculate the forward and backward pass
through your network.

Predecessor
Milestone
Successor
Critical path - Answers critical path
In your network diagram, A is a predecessor for B, C, and D. Therefore, A is a _____ activity.

Parallel
Burst
Milestone
Merge - Answers burst
To find the free slack (float) for each activity in your network diagram, you should calculate:

Early start-late start
Late start - early start
Early finish - late finish
Late finish - early start - Answers late start- early start
Your network diagram includes all the following EXCEPT:

Early start and early finish days
Calendar dates
Arrows showing precedence and flow.
Late tart and late finish days - Answers calendar dates
Scaling with a unit of measure, such as square feet or lines of code, is estimating.

Analogous
Parametric
Top down
Three-point - Answers parametric
The
_ in your budget is set aside for "unknown unknown" risks.

Activity cost estimate
Cost-baseline
Contingency reserve
Management reserve - Answers management reserve
The
helps cash flow planning and is the basis of controlling project costs &
schedule once work commences.

Work breakdown structure
Gantt chart schedule
Time phased budget
Network diagram - Answers time phased budget

, An agile approach would work best in all the following situations except:

Highly defines scope & requirements.
High level of uncertainty in the market
Developing iterations of the deliverable is ideal for the customer.
High degree of risk - Answers highly defined scope and requirements
Monitoring scrum project progress can be accomplished by using:

Backlog grooming
Burndown charts
EVM performance reports
Sprint iterations - Answers burndown charts
The impediments in scrum supports the team by facilitating daily standups and removing

Product owner
Scrum master
Developer
Quality assurance - Answers scrum master
Which of the following closing tasks occurs first?

Close contracts
Send invoice to customer.
Obtain customer acceptance.
Create closeout report. - Answers obtain customer acceptance
Ideally, lessons learned should be collected:

At the end of the execution phase
At the end of the project only
Following completion of every deliverable
Throughout the project - Answers throughout the project
In a bidding process, giving information to one vendor but not others are an ethical issue related to
this pillar:

Honesty
Responsibility
Fairness
Respect - Answers fairness
At the end of Week 2, AP "A" is 50% complete and its actual cost is 5. What is the cost variance of this
activity?
Ac: 5

a. 3
b -1
C. 1
d.-3 - Answers -3 ( EV- AC)
The development team has encountered a problem with a software feature. They need to handle this
problem quickly, but they can't make a face-to-face brainstorming session because they aren't local.
Which alternative solution is best?

videoconferencing
conference call
online chat session
email - Answers videoconferencing
One risk to your schedule is that a hard drive with customized software fails and you lose the work
that was done. Resources on the project team regularly back up their work so they can resume work
quickly after a hard drive failure. What type of risk management strategy do backups represent?

Document information

Uploaded on
June 1, 2026
Number of pages
10
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$11.89

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
joshuawesonga22
3.5
(14)
Sold
119
Followers
2
Items
15105
Last sold
23 hours ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions