Arrows can flow from left to right or from right to left. - Answers - When drawing a
network diagram, which of the following is NOT true about arrows?
Arrows can flow from left to right or from right to left.
Arrows can cross.
Arrows represent precedence.
Arrows may represent an activity or a relationship among activities.
Conditional statements are allowed but looping statements are not allowed - Answers -
Which of the following is NOT one of the basic rules to follow when developing project
networks?
Networks flow from left to right
Conditional statements are allowed but looping statements are not allowed
An activity cannot begin until all preceding activities have been completed
Each activity must have a unique identification number
Earliest time an activity can finish. - Answers - The backward pass in project network
calculations helps determine all of the following EXCEPT
The critical path.
Latest time an activity can finish.
Earliest time an activity can finish.
Latest time an activity can begin.
Schedule - Answers - The Gantt chart is used to illustrate the project _________.
Budget
Schedule
Triple Constraint
Work Breakdown Structure
Rough estimates - Answers - During project selection and chartering, what types of
budgeting is applied?
Rough estimates
None
Exact numbers
Time-phased budget estimates
Approximation - Answers - The three most commonly used methods of cost estimation
include all of the following except ______.
Analogous
Parametric
VERIFIED ANSWERS
Arrows can flow from left to right or from right to left. - Answers - When drawing a
network diagram, which of the following is NOT true about arrows?
Arrows can flow from left to right or from right to left.
Arrows can cross.
Arrows represent precedence.
Arrows may represent an activity or a relationship among activities.
Conditional statements are allowed but looping statements are not allowed - Answers -
Which of the following is NOT one of the basic rules to follow when developing project
networks?
Networks flow from left to right
Conditional statements are allowed but looping statements are not allowed
An activity cannot begin until all preceding activities have been completed
Each activity must have a unique identification number
Earliest time an activity can finish. - Answers - The backward pass in project network
calculations helps determine all of the following EXCEPT
The critical path.
Latest time an activity can finish.
Earliest time an activity can finish.
Latest time an activity can begin.
Schedule - Answers - The Gantt chart is used to illustrate the project _________.
Budget
Schedule
Triple Constraint
Work Breakdown Structure
Rough estimates - Answers - During project selection and chartering, what types of
budgeting is applied?
Rough estimates
None
Exact numbers
Time-phased budget estimates
Approximation - Answers - The three most commonly used methods of cost estimation
include all of the following except ______.
Analogous
Parametric