You are installing a 250 fpm freight elevator. what type of buffers should you use?
---------CORRECT ANSWER-----------------oil buffers
You are working in a pit deeper than normal. what can you do to bring the buffers
up to the proper height? ---------CORRECT ANSWER-----------------buffer stands
What document will tell you if you need buffer channels? ---------CORRECT
ANSWER-----------------final layout
When installing a reduced stroke buffer, what additional component is required? -
--------CORRECT ANSWER-----------------speed limiting device
You just attached a governor tension sheave to a rail. what must be done to
finalize its position? ---------CORRECT ANSWER-----------------check for plumb and
tighten all bolts.
,You are installing pit equip for a high rise elevator. which of the following is
required for an 800 fpm car? ---------CORRECT ANSWER-----------------compensating
sheave tie down
You have installed the comp rope sheave. what must you do to prepare for comp
rope install? ---------CORRECT ANSWER-----------------block the comp sheave above
normal position
You are about to perform maintenance on pit equip. what is required for oil
buffers? ---------CORRECT ANSWER-----------------check the oil level
You are working in a pit 72" deep. what does asme require regarding stop
switches? ---------CORRECT ANSWER-----------------a second stop switch must be
installed 47" above the pit floor
What would you use to connect round rails? ---------CORRECT ANSWER---------------
--bushings
You are moving rails to storage. what should be taken into consideration? ---------
CORRECT ANSWER-----------------floor load capacity
, You must stack rails on the floor of a storage room. how do they go? ---------
CORRECT ANSWER-----------------on their backs
You are installing rails with little distance between the beam and rail. what type
of bracket must you use? ---------CORRECT ANSWER-----------------angle bracket
You must fasten a bracket to a brick wall. how do you do it? ---------CORRECT
ANSWER-----------------(quick bolt that bitch) use a threaded rod and thru plate it
When installing formed guide rails, what must be done to ensure that the guide
rail is secured to the rail bracket? ---------CORRECT ANSWER-----------------rail clip
heel must contact the edge of the rail
You are installing a heavy duty freight. what clips should you use? ---------CORRECT
ANSWER-----------------forged
How much does a 16', 15lb rail weigh? ---------CORRECT ANSWER-----------------
240lbs
You are aligning t rails. which tool will help you maintain proper DBG? ---------
CORRECT ANSWER-----------------bayonet gauge
Correct Answers | Verified Answers | Graded
A+ | Just Released
You are installing a 250 fpm freight elevator. what type of buffers should you use?
---------CORRECT ANSWER-----------------oil buffers
You are working in a pit deeper than normal. what can you do to bring the buffers
up to the proper height? ---------CORRECT ANSWER-----------------buffer stands
What document will tell you if you need buffer channels? ---------CORRECT
ANSWER-----------------final layout
When installing a reduced stroke buffer, what additional component is required? -
--------CORRECT ANSWER-----------------speed limiting device
You just attached a governor tension sheave to a rail. what must be done to
finalize its position? ---------CORRECT ANSWER-----------------check for plumb and
tighten all bolts.
,You are installing pit equip for a high rise elevator. which of the following is
required for an 800 fpm car? ---------CORRECT ANSWER-----------------compensating
sheave tie down
You have installed the comp rope sheave. what must you do to prepare for comp
rope install? ---------CORRECT ANSWER-----------------block the comp sheave above
normal position
You are about to perform maintenance on pit equip. what is required for oil
buffers? ---------CORRECT ANSWER-----------------check the oil level
You are working in a pit 72" deep. what does asme require regarding stop
switches? ---------CORRECT ANSWER-----------------a second stop switch must be
installed 47" above the pit floor
What would you use to connect round rails? ---------CORRECT ANSWER---------------
--bushings
You are moving rails to storage. what should be taken into consideration? ---------
CORRECT ANSWER-----------------floor load capacity
, You must stack rails on the floor of a storage room. how do they go? ---------
CORRECT ANSWER-----------------on their backs
You are installing rails with little distance between the beam and rail. what type
of bracket must you use? ---------CORRECT ANSWER-----------------angle bracket
You must fasten a bracket to a brick wall. how do you do it? ---------CORRECT
ANSWER-----------------(quick bolt that bitch) use a threaded rod and thru plate it
When installing formed guide rails, what must be done to ensure that the guide
rail is secured to the rail bracket? ---------CORRECT ANSWER-----------------rail clip
heel must contact the edge of the rail
You are installing a heavy duty freight. what clips should you use? ---------CORRECT
ANSWER-----------------forged
How much does a 16', 15lb rail weigh? ---------CORRECT ANSWER-----------------
240lbs
You are aligning t rails. which tool will help you maintain proper DBG? ---------
CORRECT ANSWER-----------------bayonet gauge