• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 3 out of 18 pages
Exam (elaborations)

Pjm Transmission Main Exam Script Questions And Answers Sure A.pd

Document preview thumbnail
Preview 3 out of 18 pages

PJM TRANSMISSION MAIN EXAM SCRIPT QUESTIONS AND ANSWERS SURE A.pd

Content preview

PJM TRANSMISSION MAIN EXAM SCRIPT QUESTIONS AND
ANSWERS SURE A+
✔✔During system restoration, frequency has decayed for an islanded system to 59.05
Hz and is decaying rapidly. The operator should:
a) Notify PJM and seek advice
b) Call on additional generation
c) Wait for the system to settle out
d) Immediately shed load to recover the frequency - ✔✔D

✔✔If inclement weather postpones the start of a planned outage, the outage will:

a) Be postponed indefinitely
b) Be rescheduled as unplanned
c) Have to be resubmitted the following week
d) Retain its status and priority as a planned outage - ✔✔D

✔✔How long does PJM have to correct a facility that is operating above the 4-hour
emergency rating?

a) 1 minute
b) 5 minutes
c) 10 minutes
d) 15 minutes - ✔✔D

✔✔In the event of a heavy load voltage schedule, actions to increase voltage should be
taken:

a) Prior to the start of the scheduling period
b) Prior to most of the load coming in for the operating period
c) After most of the load has come in for the operating period
d) After voltage begins to decrease during the operating period - ✔✔B

✔✔What one-way communication system is used to disseminate information to local
control centers?

a) All-call
b) Email
c) Radio
d) Transaction management system - ✔✔A

✔✔When ordered, a 5% voltage reduction should be taken on:

a) The 230 kV system
b) The 500 kV system

,c) The distribution system
d) Predetermined tie lines - ✔✔C

✔✔During initial transmission system restoration, shunt capacitor banks are removed
from service to prevent which of the following?

a) High loads
b) Low voltage
c) High voltage
d) Low loads - ✔✔C

✔✔If a member detects or suspects actual or attempted sabotage on the bulk power
system, they should
1. Notify PJM immediately
2. Notify SECON immediately
3. Notify DOE within one hour
4. Notify National Guard within one hour

a) 1 and 2 only
b) 2 and 4 only
c) 1 and 3 only
d) 3 and 4 only - ✔✔C

✔✔To avoid cancellation, transmission outages that are less than 5 days in length and
may result in congestion should be submitted to PJM:

a) 7 days prior to the outage
b) 30 working days prior to the outage
c) Before the first day of the week prior to the outage
d) Before the first day of the month prior to the outage - ✔✔D

✔✔Two Transmission Owners (TOs) interconnect during a system restoration. TO A
has restored 600 MW of load. TO B has restored 2000 MW of load. Following the
interconnection, which of the following statements is true?

a) TO A and TO B both control frequency
b) TO A and TO B both control tie line flow
c) Both TOs control frequency and tie line flow
d) One TO controls tie line flow and the other TO controls frequency - ✔✔D

✔✔Which of the following are monitored during system restoration?
1. quick start reserves
2. synchronized reserves
3. operating reserves
4. dynamic reserves

, a) 1 and 2 only
b) 1 and 3 only
c) 2 and 3 only
d) 2 and 4 only - ✔✔D

✔✔A Reactive Reserve Check (RRC) consists of:

a) Unit, Capacitor/Reactor Leading MVAR reserves
b) Unit, Capacitor/Reactor Lagging MVAR reserve
c) Quickstart, Capacitor/Reactor Lagging MVAR reserves
d) Synchornous, Quickstart and Capacitor/Reactor MVAR reserves - ✔✔B

✔✔Which of the following units would receive first priority in the allocation of cranking
power during system restoration?

a) A large, centrally located steam unit that has been off for a maintenance outage and
is considered to be in a cold status
b) A large, electrically isolated steam unit that is considered to be in an intermediate
status
c) A run of river hydro unit located in the central portion of the system
d) A large, centrally located steam unit that is considered to be in a hot status - ✔✔D

✔✔An EHV line is loaded above its SIL (surge impedence loading). This line can be
considered:

a) A VAR source
b) A VAR load
c) A contingency violation
d) Over its STE (short term emergency rating) - ✔✔B

✔✔Manual Load Dump for capacity shortages is initiated:

a) Across the entire RTO on a load-ratio share basis
b) Only in control zone(s) with a deficient energy position
c) Only in the Mid-atlantic region
d) Only where it will be effective to unload the transmission line - ✔✔B

✔✔During system restoration, one means of keeping frequency above 59.5 Hz is to
activate which of the following?

a) Synchronized reserves
b) Dynamic reserves
c) Secondary reserves
d) Shared reserves - ✔✔A

Document information

Uploaded on
May 20, 2026
Number of pages
18
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BOARDWALKer
3.4
(19)
Sold
160
Followers
6
Items
26749
Last sold
3 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions