A contractor does not notify a change of address and so does not receive a timely Notice of Renewal. Who is responsible for when the contractor does not renew his license on time? - ANSWER-The Licensee Contractor A Designated Employee should be? - ANSWER-At least 18, Full Time, Passed Required Exams What is the initial Recovery Fund fee? - ANSWER-$25.00 If a contractor ears more that $_______ per year, then the contractor is required to have a Class A. - ANSWER-$750,000.00

Content preview

VA CONTRACTOR GENERAL
QUESTIONS WITH ANSWERS 100%
CORRECT
A contractor does not notify a change of address and so does not receive a timely
Notice of Renewal. Who is responsible for when the contractor does not renew his
license on time? - ANSWER-The Licensee Contractor

A Designated Employee should be? - ANSWER-At least 18, Full Time, Passed
Required Exams

What is the initial Recovery Fund fee? - ANSWER-$25.00

If a contractor ears more that $_______ per year, then the contractor is required to
have a Class A. - ANSWER-$750,000.00

If a contract awards more than $_________ per payment, the contractor is required
to have a Class A. - ANSWER-$120,000.00

An Erosion control conservation plan needs to be approved within ____ days. -
ANSWER-45

Where do you go to file an appeal of a violation to the USBC provisions? -
ANSWER-To The BBCA

A contractor is required to submit a renewal within____ days of the expiration date? -
ANSWER-30

Who can file a complaint against a contractor? - ANSWER-any one

What is required when changing the from of entity from a sole proprietorship to a
corporation - ANSWER-A new license

What is the maximum fund allowed for a single contractor? - ANSWER-$40,000.00

To Whom should the stop work order be given? - ANSWER-Owner, Owner's Agent,
Contractor

Within how many days should be submitted an appeal for construction? - ANSWER-
90 Days

Where is the Recovery Fund used? - ANSWER-to pay claimants subject to improper
or dishonest conduct

Disturbed land areas of less than ______ sq ft in size may not be an issue of
sediment and erosion control. - ANSWER-10,000

, Which of the following is permitted to receive awards from the Fund? - ANSWER-
Property Owner

An appeal of the local building officials decision to refuse to grant a modification to
the USBC MUST be made within how many days? - ANSWER-90 Days

Documents related to a contract should be kept for ______ years? - ANSWER-5
Years

Where should one set of all approved building documents be kept? - ANSWER-At
the building site

An erosion control conservation specification needs to be approved within_____
days - ANSWER-60 days

After notification by the code official, an application for a permit shall be considered
to have been abandoned for _____ months - ANSWER-6

The Board can refuse to renew a license when the principal owner is a former owner
or officer of a firm that______ - ANSWER-Had its contractor licensee revoked

what is the maximum amount a single contractor's Transaction Recovery Fund claim
against a licensee can be? - ANSWER-$40,000.00

What is the maximum amount that can be paid out on behalf of a single contractor? -
ANSWER-$40,000.00

A license was issued on 10/15/2003. The expiration date is? - ANSWER-10/31/2005

A designated employee must work a minimum of how many hours for licensed
contracting business? - ANSWER-30 Hours

Where must a building permit be kept? - ANSWER-at the building site

Who may make a claim for a payment from the contractors Recovery Trust Fund? -
ANSWER-a property owner who contracted with the licensee

A permit has been issued and construction is underway. The inspection must take
place in? - ANSWER-six months

Soil stabilization MUST be applied to denuded areas within how many days after
final grade is reached on any portion of the site? - ANSWER-7 days

A contractor must apply for reinstatement rather than renewal if the renewal
application and fee are not submitted within how many days of expiration? -
ANSWER-30 days

A new building may be used after ______________ is issued. - ANSWER-certificate
of occupancy

Document information

Uploaded on
May 15, 2026
Number of pages
5
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
1
Followers
0
Items
190
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions