This document contains revised questions and verified correct answers for Erosion and Sediment Control Test 1. It covers key concepts such as soil erosion processes, sediment management techniques, and best management practices (BMPs). The material is useful for exam preparation and reinforces understanding through updated and clarified questions. It is suitable for students reviewing foundational and applied erosion control strategies.

Content preview

Erosion and Sediment Control Test 1 with
revised questions and correct answers
2-year, 24-hour storm even - CORRECT ANSWERS-maximum 24-hour precipitation event with a probable
recurrence interval of once in two years as defined by the National Weather Service and Technical Paper
No. 40, "Rainfall Frequency Atlas of the US" May 1961 or equivalent regional rainfall probability
information developed there from



24-hour Precipitation Event - CORRECT ANSWERS-amount of precipitation which occurs within any 24
hour period



AEMA - CORRECT ANSWERS-Alabama Environmental Management Act, Code of Alabama 1975



Alabama Handbook - CORRECT ANSWERS-current edition of the Alabama Handbook for Erosion Control,
Sediment Control, and Stormwater Management on Construction Sites and Urban Areas published by
the Alabama Soil and Water Conservation Committee (ASWCC) at the time permit coverage is obtained



ADEM - CORRECT ANSWERS-Alabama Department of Environmental Management



Agricultural Practices - CORRECT ANSWERS-practices commensurate with the size of the farming
operation that are implemented in a manner that meet or exceed the Natural Resources Conservation
Service technical standards and guidelines, including but not limited to farm ponds that are constructed
for the primary purpose of irrigation and/or watering livestock, terraces, grassed waterways, vegetative
filter strips, cropland grade stabilized measures drainage tiles, underground outlets, land leveling,
dike/diversion structures and other grade stabilized structures



AWPCA - CORRECT ANSWERS-Alabama Water Pollution Control Act



Best Management Practices (BMPs) - CORRECT ANSWERS-implementation and continued maintenance
of appropriate structural and non-structural practices and management strategies to prevent and
minimize the introduction of pollutants to stormwater and to treat stormwater to remove pollutants
prior to discharge

, Borrow Area "Pit" - CORRECT ANSWERS-the activity of removing material (soil, gravel, sand) from one
area to use in another area. For the purposes of this

permit, this activity is solely in conjunction with the project requesting permit coverage and the material
is not to be sold for profit. The borrow

area and associated activity shall be located within a two-mile radius of the project requesting permit
coverage to be considered as part of the

project and will open and close with the project requesting permit coverage



Chronic and Catastrophic Precipitation - CORRECT ANSWERS-precipitation events which may result in
failure of the properly designed, located, implemented,

and maintained BMPs or other structure/practices required by this permit. Catastrophic precipitation
conditions means any single event of

significant total volume, or of increased intensity and shortened duration, that exceeds normally
expected or predicted precipitation over the time

period that the disturbance is planned or is ongoing, as determined by the Department. Catastrophic
conditions could also include tornadoes,

hurricanes, or other climatic conditions which could cause failure due to winds or mechanical damage.
Chronic precipitation is also that series of

wet-weather conditions over a limited time-period which does not provide any opportunity for
emergency maintenance, reinstallation, and

corrective actions and which equals or exceeds the volume of normally expected or predicted
precipitation for the time period that the disturbance

is planned or is ongoing



Common Plan of Development or Sale - CORRECT ANSWERS-any announcement or piece of
documentation (e.g., sign, public notice, or hearing, sales pitch,

advertisement, drawing, permit application, zoning request, computer design, etc.) or physical
demarcation (e.g., boundary signs, lot stakes,

surveyor markings, etc.) indicating construction activities may occur on a specific plot

Document information

Uploaded on
May 1, 2026
Number of pages
13
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
121
Last sold
-


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions