Summary of lecture notes from the Project Management course at Universiteit Gent's Master of Business Engineering (Operations Management) program. Covers baseline scheduling fundamentals including PERT methodology with three-point estimation, CPM network analysis, and project phase structure (definition, scheduling, execution, control). Topics include the project triangle trade-offs, Work Breakdown Structure (WBS), Activity-on-Node (AON) vs Activity-on-Arc (AOA) networks, forward/backward pass scheduling, and critical path analysis with practical examples. Essential reference material for understanding deterministic scheduling in low complexity/low risk projects and preparing for project management assessments.

Show more Read less
Institution
Course

Content preview

1. Introduction
A project is a temporary endeavor with a defined beginning and end, undertaken to meet unique
goals and objectives and to create beneficial or added value. The classic project triangle shows
the trade-off between cost, time and specifications, where improving one dimension typically
affects the others

Scheduling covers all static planning work done before project execution, whereas control
refers to dynamic activities during project progress.
Risk analysis forms a feedback loop between scheduling and control: risk is analyzed in advance
in a static way, while actual risk happens during the dynamic execution phase.

Project mapping positions projects along two axes: complexity (resources) and uncertainty
(risk).

• Low uncertainty and low complexity lead to baseline scheduling with
PERT/CPM. Example: Fabricom: luggage systems, 5-6 people, no huge risk.

• High risk and low complexity lead to Scheduling Risk Analysis (SRA). Example:
Brabantia, 3-4 people, marketing success defined at the end = risk.

• High complexity and low risk point to Critical Chain scheduling (CC). Example: Water
infrastructure.

• High complexity and high risk lead to Critical Chain/Buffer Management (CC/BM),
where buffers are added to protect against risk. Example: NPD, development iPhone: no
idea what to expect at the end of the project.


2. Baseline Scheduling
2.1. PERT basics
PERT (Program Evaluation and Review Technique) uses three time estimates for each activity: a
(best), m (realistic), and b (worst). Activity durations are assumed to follow a right-skewed beta
distribution, closer to the worst case than to the best case.

Formulas:

• Expected duration: (𝑎 + 4𝑚 + 𝑏)/6

• Standard deviation: (𝑏 − 𝑎)/6

The procedure is:

1. Define three time estimates per activity.

2. Compute average and standard deviation per activity.

3. Determine the average critical path duration.

4. Apply the Central Limit Theorem to approximate total project duration.

5. Use statistical insight to support decisions.

, 2.1.1. Strengths & Weaknesses
Average of CPM close to 50/50, but actual 44/56 (error is low)

• Estimates are human input (3 estimates better than 1, “garbage in, garbage out”)
• Simplifications of statistics (assumption no correlation: standard deviation)
• PERT ignores non-critical activities (can become critical -> stdev & CLT not correct)

2.2. CPM and the project phases
CPM (Critical Path Method) focuses on deterministic durations and is especially suited to low
complexity, low risk projects. Capacity increase (new water towers, pipeline, machines,
buildings): not easy but not extremely complex.

The logic of phases:

• Concept →

• Definition (what?), static →

• Scheduling (when?), static →

• Execution, dynamic (Mister Murphy) →

• Control →

• Termination.

In the definition phase, a global plan is prepared, including:

• A(1): determination of activities via a Work Breakdown Structure (WBS)

• P(2): responsibility assignment (possibly external experts)

• L(3): sequencing and linking of activities

• N(4): network analysis providing input for scheduling tools (output of definition phase)

The WBS breaks down the project objective into

• Root node
• Work items (building machines, define work items -> expertise) (not only 1/WI)
• Work packages
• Activities

Where the lowest level corresponds to the highest level of detail; each level has a specific
functionality.
This is related to the Organization Breakdown Structure (OBS): project objective → work items
→ work packages → activities.
VMW definition phase with two parts (reservoir and new machines) due to different objectives
(time vs cost).

Part1: increase reservoir: very urgent, more water during peak needed now!!: obj = time
Part2: new machines for bigger capacity not so urgent (more demand only in 6-7 years) obj: cost

Written for

Institution
Study
Course

Document information

Uploaded on
April 28, 2026
Number of pages
12
Written in
2025/2026
Type
SUMMARY

Subjects

$7.08
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
elisedeleu

Get to know the seller

Seller avatar
elisedeleu Universiteit Gent
Follow You need to be logged in order to follow users or courses
Sold
-
Member since
2 months
Number of followers
0
Documents
2
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions