ICC Code Specialist (CS) Certification Exam Actual
Test||Verified Questions and Correct Answers With
Rationales LATEST THIS YEAR.pdf 1||NEWEST
EXAM!!!
Who is in charge of giving "approval to proceed"
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-A
Who responds to reports of uncorrected discrepancies?
A) The building official
B) the contractor
C) The owner
D) The RDP - Answer-D) The RDP
What does a special inspector's job NOT entail while on
the job site?
A) instructing the contractor;s workers on how to do their
job
,2|Page
B) Verify means and methods of construction
C) Inform the contractor of arrival
D) Discuss with the contractor any discrepancies as they
may come up later in a lawsuit - Answer-A) Instructing the
contractor's workers on how to their job
What should a special inspector NOT do prior to arriving to
the jobsite?
A) Attend a preconstruction meeting
B) Review the construction documents
C) Discuss frequency of reports with the building official
D) Ask any questions you may have - Answer-A) Attend a
preconstruction meeting
Who performs a structural observation?
A) the RDP in responsible charge
B) The special inspector
C) The contractor
D) The building official - Answer-A) the RDP in responsible
charge
Who prepares the statement of special inspections?
,3|Page
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-D) The RDP
Who is in charge of reviewing and approving reports?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-D) The RDP
ICC exams are based on which document?
a) ACI
b) IBC
c) ASTM - Answer-B) IBC
Which of the following should a special inspector contact
the contractor about immediately?
A) If the concrete temperature is 80 degrees
B) If the slump calls for a maximum of 4' but is 6'
, 4|Page
C) If the air content calls for 6% but is 3%
D) If the steel isn't tied properly - Answer-B and C
Can a material not listed in the IBC be used for
construction?
A) Yes
B) No - Answer-A
Who should NOT hire the special inspector?
A) The building official
B) The contractor
C) The Owner
D) The RDP - Answer-B
Who's job is it to ensure that the special inspector has an
approved set of plans?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-B
ICC Code Specialist (CS) Certification Exam Actual
Test||Verified Questions and Correct Answers With
Rationales LATEST THIS YEAR.pdf 1||NEWEST
EXAM!!!
Who is in charge of giving "approval to proceed"
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-A
Who responds to reports of uncorrected discrepancies?
A) The building official
B) the contractor
C) The owner
D) The RDP - Answer-D) The RDP
What does a special inspector's job NOT entail while on
the job site?
A) instructing the contractor;s workers on how to do their
job
,2|Page
B) Verify means and methods of construction
C) Inform the contractor of arrival
D) Discuss with the contractor any discrepancies as they
may come up later in a lawsuit - Answer-A) Instructing the
contractor's workers on how to their job
What should a special inspector NOT do prior to arriving to
the jobsite?
A) Attend a preconstruction meeting
B) Review the construction documents
C) Discuss frequency of reports with the building official
D) Ask any questions you may have - Answer-A) Attend a
preconstruction meeting
Who performs a structural observation?
A) the RDP in responsible charge
B) The special inspector
C) The contractor
D) The building official - Answer-A) the RDP in responsible
charge
Who prepares the statement of special inspections?
,3|Page
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-D) The RDP
Who is in charge of reviewing and approving reports?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-D) The RDP
ICC exams are based on which document?
a) ACI
b) IBC
c) ASTM - Answer-B) IBC
Which of the following should a special inspector contact
the contractor about immediately?
A) If the concrete temperature is 80 degrees
B) If the slump calls for a maximum of 4' but is 6'
, 4|Page
C) If the air content calls for 6% but is 3%
D) If the steel isn't tied properly - Answer-B and C
Can a material not listed in the IBC be used for
construction?
A) Yes
B) No - Answer-A
Who should NOT hire the special inspector?
A) The building official
B) The contractor
C) The Owner
D) The RDP - Answer-B
Who's job is it to ensure that the special inspector has an
approved set of plans?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-B