Reliability Certification
Which one of the following is generally true - correct answer ✔✔Reliability Centered
Maintenance can be applied on capital projects in the pre-construction stage to determine the
maintenance plan
What are the three most significant constraints when developing a Maintenance and Reliability
organization? - correct answer ✔✔culture, people, resources.
Weibull (life data) analysis is primarily used for... - correct answer ✔✔Probability of failure
determination
A large manufacturing company installed some asset monitoring device on some large motors
that were deemed critical equipment. The monitoring devices provide engineering with
vibration data, acoustic data as well as operational performance data. What asset management
strategy has the company selected for the motors? - correct answer ✔✔CBM / PDM
(Conditioned Based Maintenance / Predictive Maintenance)
If a Machine is run for 500 hours and 5 failures are observed during this period, what is the
Mean Time Between Failure? - correct answer ✔✔500/5 = 100 hours
Which of the following most effectively makes up the members of a Manufacturing Team? -
correct answer ✔✔Production / Maintenance / Supplier / Engineering
A skill audit is undertaken to ... - correct answer ✔✔Help an organization understand skills it
requires
Of the following, what is the best method of measuring employee skills and training? - correct
answer ✔✔Maintaining a skills inventory and tracking database
, When training maintenance workers, it is best to first... - correct answer ✔✔List all the tasks the
workers need to perform
What relationship should Maintenance and Reliability Teams have with customers and suppliers
for optimum effectiveness? - correct answer ✔✔Team members should be involved in
communicating with customers and suppliers
Return on Asset (ROA) is determined by... - correct answer ✔✔Revenue/Total Assets
As a maintenance manager at a new plant (facility) you are developing the maintenance
workforce strategy for start-up. Select the best workforce attributes for maximum effectiveness,
assuming that unit labor cost are equal. - correct answer ✔✔Operation performing minor
maintenance and company multi-skilled technicians performing complex maintenance tasks.
Which of the following are leading tools or techniques to identify Maintenance and Reliability
process improvements? - correct answer ✔✔Total Productive Maintenance, Reliability Centered
Maintenance & Process bench-marking with industry leaders.
For the oil and pressurized lubrication system, oil samples for analysis and trending should be
taken from... - correct answer ✔✔The oil sump, at a point above the bottom to assure that the
sample does not include wear particles, water and other contaminants that may have settled
out of the oil.
The "Karl Fischer Method" measures - correct answer ✔✔The amount of water in a sample of
oil in ppm.
When developing and presenting a new strategic plan to stakeholders, which of the following is
the most important? - correct answer ✔✔Gain the trust of stakeholders