Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 39 pages
Exam (elaborations)

WGU C170 EXAM 2 QUESTIONS AND VERIFIED CORRECT ANSWERS GRADED A-LM -LATEST -L1 GUARANTEED PASS.docx

Document preview thumbnail
Preview 4 out of 39 pages

WGU C170 EXAM 2 QUESTIONS AND VERIFIED CORRECT ANSWERS GRADED A-LM -LATEST -L1 GUARANTEED PASS.docx

Content preview

WGU – C170 EXAM 2
QUESTIONS AND VERIFED
CORRECT ANSWER GRADED
A+ LATEST 2026-2027 100%
GUARANTEED PASS


deliverable - CORRECT ANSWER-is a specific product or functionality that the project will
provide.



Activities are connected to two types of deliverables: - CORRECT ANSWER-Project management
- communications, planning, execution, etc.

Project specific to the desired end result of this project



8/80 rule - CORRECT ANSWER-do not assign anything that takes less than eight hours so we
allow resources sufficient work to occupy them and we don't micromanage



Project management deliverables - CORRECT ANSWER-the concrete items we need to manage
this project. They are usually generic to a business or methodology adopted by a PM for use to
manage the team and create sound communications.



Project specific deliverables - CORRECT ANSWER-project specific deliverables are required tasks

,Risk Appetite - CORRECT ANSWER-is the degree of uncertainty an entity is willing to take on in
anticipation of a reward.



Risk Tolerance - CORRECT ANSWER-is the degree, amount, or volume of risk that an
organization or individual will withstand.



Risk Threshold - CORRECT ANSWER-refers to measurements along the level of uncertainty or
the level of impact at which a stakeholder may have a specific interest. Below that risk
threshold, the organization will accept the risk. Above that risk threshold, the organization will
not tolerate the risk (PMBOK, 2015).



Risk Planning - CORRECT ANSWER-is the process of reviewing every aspect of the project to
identify what risks may occur.



Risk Breakdown Structure (RBS) - CORRECT ANSWER-which follows the WBS and insures that
each activity and task in the WBS is reviewed for risk and opportunity and documented as
identified.



Risk Management Options - CORRECT ANSWER-Avoid, mitigate, transfer and accept.



Risk Avoidance - CORRECT ANSWER-During our planning, the team identifies the risk and sets a
path to avoid the risk.



Transfer of the risk - CORRECT ANSWER-transfer risk to someone else



Mitigation - CORRECT ANSWER-is when the team acts in some fashion to reduce the impact or
likelihood of the risk occurring.

,Accepting - CORRECT ANSWER-the risk is a response strategy where we recognize the risk and
say that it is a part of the project, normal business practice and the team will plan to accept it
accordingly.



Opportunity Management - CORRECT ANSWER-Acceptance, Enhancing the opportunity and
Sharing the opportunity



risk register - CORRECT ANSWER-lists all risks (external, technical, or organizational) and assigns
scores for probability and severity.



Probability Severity (P*S) score - CORRECT ANSWER-helps us prioritize the risks appropriately.



top-down estimation methods - CORRECT ANSWER-hese estimates are often provided by
someone at the organization who has knowledge or experience from prior projects similar to
the project being considered



Bottom-up estimation methods - CORRECT ANSWER-require that estimates be made at the
detailed work activity level of the WBS.



parametric estimating - CORRECT ANSWER-top-down methods are based on the relationship
between the current project and historical data



ratio method - CORRECT ANSWER-uses experience from prior projects to estimate the overall
cost of the current project.



apportion method - CORRECT ANSWER-is based on the ratio method but takes into
consideration specific functionality or types of work that will be required.



Cost management - CORRECT ANSWER-is the process of measuring how close actual costs are
to the budget and then making changes in project execution as needed.

, baseline budget - CORRECT ANSWER-is the approved budget and will be used as the standard
for comparison of actual costs throughout the life of the project and identifying variances.



Direct costs - CORRECT ANSWER-are costs that are directly attributable to completing the
project work.



Direct overhead costs - CORRECT ANSWER-are costs from the project that are shared across the
work activities.



General and administrative costs (G&A) - CORRECT ANSWER-are overhead costs from the
project organization.



padding - CORRECT ANSWER-people tend to add in extra time or money "just in case."



Contingency reserves - CORRECT ANSWER-are costs included in the budget to cover situations
that may occur. If the project requires the use of lumber, and lumber prices are known to
fluctuate, then some portion of the lumber costs may be included in a contingency reserve. In a
restaurant, food costs are very volatile and so the project must budget for those variances that
can occur



management reserve - CORRECT ANSWER-is an amount added to the overall project budget to
cover unknown risks.



Realistic - CORRECT ANSWER-Accurately reflects the way the organization does business.

Appropriate for the level of resources, capabilities, and external environment of the
organization.



Capable - CORRECT ANSWER-Uses factors that are relevant to the organization.

Document information

Uploaded on
April 21, 2026
Number of pages
39
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
examhandler01
4.7
(6)
Sold
32
Followers
6
Items
3260
Last sold
6 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions