◉What are the Contractor Responsibilities in quality assurance?
Answer: The contractor is responsible for:
Controlling the quality of supplies or services
Deliver to the Government only those supplies or services that
conform to contract requirements
Ensuring that vendors or suppliers have an acceptable quality
control system
Maintaining substantiating evidence that the supplies or services
conform to contract quality requirements And furnishing such
information to the Government as required.
◉What is the Quality Assurance Surveillance Plan (QASP)? Answer:
is the key Government-developed surveillance process document
that is applied to Performance-Based Service Contracting (PBSC)
and is used to manage contractor performance assessment by
ensuring that systematic quality assurance methods are utilized to
validate that the contractor's quality control efforts are timely,
, effective, and are delivering the results specified in the contract or
task order.
◉What are Excusable Delays? Answer: -Protect the contractor from
sanctions for late performance when the event is
"beyond the control" of the contractor;
without "fault or negligence" of he contractor;
unforeseeable.
Gives the contractor more time, but not money
◉What are Compensable (Govt.)Delays? Answer: Delays generally
directed by the KO IAW:
-Suspension of Work clause under construction contracts
-Stop Work clause; supplies, services, or R&D
-Government Delay of Work, mandatory for FFP non-commercial
supplies
-Remedy (time & money)
◉What are Contractor Delays? Answer: These are all considered to
be within the contractor's control and are not excusable
Normally not excused from delays due to:
PRESENTING ACCURATE ANSWERS
GRADED A+
◉What are the Contractor Responsibilities in quality assurance?
Answer: The contractor is responsible for:
Controlling the quality of supplies or services
Deliver to the Government only those supplies or services that
conform to contract requirements
Ensuring that vendors or suppliers have an acceptable quality
control system
Maintaining substantiating evidence that the supplies or services
conform to contract quality requirements And furnishing such
information to the Government as required.
◉What is the Quality Assurance Surveillance Plan (QASP)? Answer:
is the key Government-developed surveillance process document
that is applied to Performance-Based Service Contracting (PBSC)
and is used to manage contractor performance assessment by
ensuring that systematic quality assurance methods are utilized to
validate that the contractor's quality control efforts are timely,
, effective, and are delivering the results specified in the contract or
task order.
◉What are Excusable Delays? Answer: -Protect the contractor from
sanctions for late performance when the event is
"beyond the control" of the contractor;
without "fault or negligence" of he contractor;
unforeseeable.
Gives the contractor more time, but not money
◉What are Compensable (Govt.)Delays? Answer: Delays generally
directed by the KO IAW:
-Suspension of Work clause under construction contracts
-Stop Work clause; supplies, services, or R&D
-Government Delay of Work, mandatory for FFP non-commercial
supplies
-Remedy (time & money)
◉What are Contractor Delays? Answer: These are all considered to
be within the contractor's control and are not excusable
Normally not excused from delays due to: