Points: 50/50
Correct 3/3 Points
1. Which one of the following contract types is considered an incentive type
contract?
Time and Material Contract
Cost Contract
Cost Plus Award Fee Contract
Feedback: Correct, see FAR 16.401(e) and FAR 16.405-2. See U07
student slide 105. Firm-Fixed Price
Correct 3/3 Points
2. Which of the following statements correctly identifies when an indefinite-delivery
contract is appropriate to use?
When the specifications/work statement is clearly defined.
When it is possible to estimate accurately the extent of and duration of the
work.
When the exact times and/or quantities of future deliveries are not known at time of
award.
Feedback: Correct, see FAR 16.501-2(a). See U07 student slides 15 and 16.
, When uncertainties involved in contractor performance do not permit costs to
be estimated.
Correct 3/3 Points
3. Which one of the following is a characteristic of cost reimbursable type contracts?
Requires maximum government surveillance.
Feedback: Correct, see FAR 16.301-3(a)(4). See U07 student slide 9.
The contractor shall deliver or risk default.
Profit is not limited.
The risk to the contractor is high.
Correct 3/3 Points
4. Contracting may employ simplified acquisition procedures for acquisitions of
commercial items not exceeding:
$7,500,000
Feedback: Correct, see FAR 13.500(a) . See U07 student slides 34 through 37.
$1,000,000
$250,000
$2,500
Correct 3/3 Points
5. Select the statement that is INCORRECT when it comes to the requirement to use
sealed bidding: