• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 2 out of 11 pages
Exam (elaborations)

ICC Prestressed Concrete - Codes and Plans Certification Preparation with all Correct & 100% Verified Answers |Already Graded A+

Document preview thumbnail
Preview 2 out of 11 pages

ICC Prestressed Concrete - Codes and Plans Certification Preparation with all Correct & 100% Verified Answers |Already Graded A+

Content preview

ICC Prestressed Concrete - Codes and Plans
Certification Preparation with all Correct & 100%
Verified Answers |Already Graded A+

Module 1. Prestressed concrete is: ✔Correct Answer-- The tensioning of steel-stranded cables prior
to concrete placement
- The tensioning of steel-stranded cables after concrete has been placed and hardened
- Concrete that has received a tensile load prior to any service loads

Module 1. The use of a prestressed concrete system will achieve the following: ✔Correct Answer--
Reduced thickness of concrete, less conventional reinforcing steel and adequate crack control

Module 1. Once tensioned, the tensioning cables are held securely in a tensioned state by:
✔Correct Answer-Wedges that have been seated

Module 1. The end of a cable that terminates within a concrete slab, thus rendering it in accessible
from outside the concrete is known as: ✔Correct Answer-The dead end

Module 1. The presence of sheathing on a wire-stranded cable indicates that: ✔Correct Answer-It
will be used in an unbonded system application

Module 1. The most common post-tension cable tendons in use today are made up of: ✔Correct
Answer-7 steel strands of wire wrapped together

Module 1. In an unbonded system, the force applied to the concrete after tensioning: ✔Correct
Answer-Comes from the anchorage zone only

Module 2. Post-tension manufacturing plants must be certified by: ✔Correct Answer-PTI
Unbonded Plant Certification Program

Module 2. Prior to cutting the tendon tails after tensioning, the field records of stressing activities
must be forwarded to and approved by: ✔Correct Answer-The engineer of record

Module 2. In the event that a new set of stressing equipment is delivered to the project, this
equipment should contain __________ for review prior being used on-site: ✔Correct Answer-A
current calibration chart relating gauge pressure to force applied

Module 2. According to the Field Procedures Manual for Unbonded Single Strand Tendons, all of the
following items are necessary for post-tension document control except:
A) Concrete Strength Results
B) Shipping Lists
C) Material Certifications
D) Approved Installation Drawings ✔Correct Answer-A) Concrete Strength Results

Module 2. When reporting stressing results, the following information is necessary to record:
A) Jack and gauge serial number
B) Elongation measurements and percentage deviation
C) Both A and B

, D) Gauge Manufacturer
E) All three, A, B, and D ✔Correct Answer-C) Both A and B

Module 2. When moving post-tension cables across the site, the use of _______ is permitted.
A) Nylon slings, with unloading as close as placement as possible
B) Smooth finished chains with limited use
C) Epoxy coated high strength wire with limited use
D) A large front loader exercising caution ✔Correct Answer-Nylon slings, with unloading as close to
the placement as possible

Module 2. When storing post-tension cables, care must be taken to: ✔Correct Answer-Prevent the
cables from being exposed to weather elements and moisture

Module 2. During deliver, it is the ______________ responsibility to ensure the delivered items
match the shipping list. ✔Correct Answer-Buyer's

Module 2. According to the Field Procedures Manual for Unbonded Single Strand Tendons, the follow
documents must be kept on site: ✔Correct Answer-1) Approved Installation Drawings
2) Shipping Lists
3) Material Certifications
4) Jack Calibrations
5) Stressing Records

Module 2. Install drawings show: ✔Correct Answer-Plan views, elevation views, and details so the
subcontractor and inspector can clearly see the tendon layout. This includes tendon profiles, also
known as drape.

Module 2. Drape ✔Correct Answer-Tendon profiles

Module 2. Material Certifications ✔Correct Answer-Documents that describe the cables' physical
properties and factory testing results.

Module 2. Stressing records, written by the inspector, should include: ✔Correct Answer-- Location
of tendons stressed (grid line to grid line)
- Type of tendons stressed (banded, uniform, beans, temperature)
- Gauge/jack used
- Date, time, and weather during stressing
- Stressing crew
- Elongations based on a traceable numbering system
- Any deviations from tolerances

Module 2. As an inspector, you should immediately check for ____________ when you see the
stressing equipment. I.e., not on the day of stressing. ✔Correct Answer-Jack Calibration Records

Module 3. On a two-way flat plate, a minimum of ___________ over each column first.
A) 2 uniform tendons should be placed
B) 1 group of banded tendons should be placed
C) 50% of the bottom bars should be placed
D) (3) #5 support bars should be placed ✔Correct Answer-A) 2 uniform tendons should be placed

Document information

Uploaded on
March 17, 2026
Number of pages
11
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Stuvia2026
2.3
(3)
Sold
26
Followers
1
Items
6370
Last sold
2 weeks ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions