ACTUAL EXAM WITH VERIFIED
QUESTIONS AND CORRECT ANSWERS
GRADED A+ || 100% GUARANTEED PASS
LATEST UPDATED VERSION
PCIC Equation - Answer PCIC = AC / EAC
Actual Cost / Estimated Cost at Completion
ETC - Answer Estimate to Completion
How much money will need to complete the project
ETC = (BAC - EV)/CPI
(Budget at Completion - Earned Value) /
Cost Performance Index
CPI = EV/AC
EAC - Answer Estimate at Completion
Forecast of how much more the project is expected to cost to complete
EAC = AC + ETC
,Actual Cost = Estimate to Completion
ETC = (BAC - EV)/CPI [Cost performance index]
CPI = EV/AC
EVA - Answer Earned Value Assessment
EVA Process Step 1 - Answer Collect measures from project records:
1. AC - Actual Cost
2. EV - Earned Value
3. PV - Planned Value
4. BAC - Budget at Completion
EVA Process Step 2 - Answer Calculate Variances:
1. CV - Cost Variance
2. SV - Schedule Variance
3. PCIB - Percent complete index budget
EVA Process Step 3 - Answer Calculate Performance Factors
1. CPI - Cost Performance Index
2. SPI - Schedule Performance Index
EVA Process Step 4 - Answer Calculate Estimates or Identifying Performance
Factors
1. ETC - Estimate to completion
,2. EAC - Estimate at completion
3. TCPI - To complete performance Index
4. PCIB - Percent complete index budget or
PCIC - (Percent complete index - cost)
operations - Answer are the ongoing, daily activities of an organization that
produces revenue and expense.
project - Answer is an activity or group of activities to generate a new, unique
product, service, or results to support that program. However, it is possible that not
all projects will be part of a larger program. There could, for example, be a project
to develop a new battery that is more adaptable to more extreme temperature
conditions. The product of this project could be applicable to all existing
automobiles and not strictly a single program.
portfolio - Answer is a group of related programs that support a long-term
company goal or objective. The projects in a portfolio may individually address
separate initiatives within the organization but collectively move the organization
toward meeting a long-term goal or objective.
business strategy - Answer consists of the activities, methods, tactics, etc. that
will be employed to meet the business's goals.
program - Answer is a group of related projects.
project management - Answer the application of knowledge, skills, tools and
techniques to project activities.
, Phases of the Project Life Cycle - Answer Defining (intializing), Planning,
executing and closing
Defining - Answer Determining the project's sponsor and the project's manager
Creating a project charter. The charter is a document that, like a contract, is agreed
upon by the sponsor and key stakeholders. It defines the project and authorizes the
resources, roles, responsibilities, authorities, and scope for the project.
Planning - Answer Technology
Business process
Staffing
Training
Testing
Communications
Budget constraints
Integration of the project with operations and other projects
Executing - Answer Unexpected changes that may present themselves in the
competitive environment
New organizational priorities
Loss of key project resources
Previously unidentified risks surfacing that puts the project plans in jeopardy
Closing - Answer The closing phase of the project occurs when the project is
completed to the customers' satisfaction.